Jump to Content Jump to Main Navigation
Signed in as:

Part VI The Award, Ch.24 Post–Award Proceedings

David D. Caron, Lee M. Caplan, Matti Pellonpää

From: The UNCITRAL Arbitration Rules: A Commentary (1st Edition)

David D. Caron, Matti Pellonpää, Lee M. Caplan

A newer edition of The UNCITRAL Arbitration Rules is available. Latest edition (2 ed.)
Next Edition: 2nd Edition Latest edition (2 ed.)

From: Oxford Legal Research Library (http://olrl.ouplaw.com). (c) Oxford University Press, 2023. All Rights Reserved. Subscriber: null; date: 06 June 2023

(p. 879) Chapter 24  Post–Award Proceedings

  1. Introduction 880

  2. Interpretation of the Award–Article 35 880

    1. Text of the UNCITRAL Rule 880

    2. Commentary 881

    3. Extracts from the Practice of the Iran-US Claims Tribunal 885

    4. Extracts from the Practice of NAFTA Tribunals 891

    5. Extracts from the Practice of Ad Hoc Tribunals 892

  3. Correction of the Award–Article 36 894

    1. Text of the UNCITRAL Rule 894

    2. Commentary 895

    3. Extracts from the Practice of the Iran-US Claims Tribunal 898

      1. (1)  Request for Correction Granted 898

      2. (2)  Request for Correction Denied 900

  4. Additional Award–Article 37 908

    1. Text of the UNCITRAL Rule 908

    2. Commentary 908

    3. Extracts from the Practice of the Iran-US Claims Tribunal 911

      1. (1)  Request for Additional Award Granted 911

      2. (2)  Request for Additional Award Denied 911

  5. The Finality of Awards and the Inherent Power to Reconsider 914

    1. Commentary 914

    2. Extracts from the Practice of the Iran-US Claims Tribunal 919

      1. (1)  Limited Power of Review 919

      2. (2)  Revision to Address Fraud or Corruption 921

    3. Extracts from the Practice of NAFTA Tribunals 924

    4. Extracts from the Practice of Ad Hoc Tribunals 925

(p. 880) Introduction

Among the most important obligations that the arbitral tribunal owes the parties is the rendering of a coherent, accurate, and complete award.1 Because international arbitration often involves complex claims adjudicated at a quick pace by arbitrators who may not be operating in their native language, ambiguities, mistakes, and omissions can taint the final product–perhaps to the point of compromising the validity of the award. To allow the arbitrators to rectify these problems, Articles 35, 36 and 37 of the UNCITRAL Rules, respectively, grant the arbitral tribunal post–award authority to interpret, correct, and complete an award, if necessary.2 In so doing, they provide a narrow exception to the basic rule of finality of awards.3 Articles 35, 36 and 37, however, are not mechanisms by which a party may reargue its case or introduce new arguments or claims for resolution by the arbitral tribunal. In addition to interpretation, correction and completion of an award, this Chapter addresses the debatable subject of an arbitral tribunal's inherent power to revise an award in the event of fraud or corruption.

Interpretation of the Award–Article 35

Text of the UNCITRAL Rule4

Article 35 of the UNCITRAL Rules provides:

  1. 1.  Within thirty days after the receipt of the award, either party, with notice to the other party, may request that the arbitral tribunal give an interpretation of the award.

  2. 2.  The interpretation shall be given in writing within forty–five days after the receipt of the request. The interpretation shall form part of the award and the provisions of article 32, paragraphs 2 to 7, shall apply.

(p. 881) Commentary

Unfortunately, in some cases, the terms of an award may be written unclearly, obscuring the arbitral tribunal's decision on the claims presented by the parties. Article 35 of the UNCITRAL Rules establishes a procedure whereby a disputing party may request the arbitral tribunal to provide an interpretation of a previously rendered award. Interpretation, as distinguished from other post–award proceedings, provides “clarification of the award” by resolving any ambiguity and vagueness in its terms.5 Interpretation may be particularly useful in the context of a continuing business relationship, where because of the award's unclear terms the parties require further guidance from the arbitral tribunal on the meaning of their future obligations.6

The interpretation process does not provide grounds for review “when a party seeks to reargue the case or disagrees with the conclusions reached by the Tribunal.”7 Nor does it allow a party to raise new arguments or introduce (p. 882) new evidence.8 These rules have been confirmed on numerous occasions at the Iran-US Claims Tribunal when Iran invoked Article 35 (along with Articles 36 and 37 in some cases)9 as a basis for the Tribunal to reconsider an adverse award. In every case, the Tribunal rejected Iran's request as being both beyond the scope of Article 35 and in violation of the rule of finality of awards contained in Article 32(2).

According to Article 35, upon the request of a party, an interpretation “shall be given.” This mandatory requirement naturally applies only to requests for interpretation that fall within the scope of Article 35, as determined by the arbitral tribunal. An arbitral tribunal is thus not required to render an interpretation in the absence of a real need to clarify the meaning of the award.10 It is nevertheless good practice for the arbitral tribunal to set forth its reasons for rejecting a request for interpretation in an explanatory decision. The arbitral tribunal has no authority to interpret an award sua sponte in the absence of a party's request.

What legal effect does a post–award interpretation have on the parties, when under many national arbitration laws an arbitral tribunal's jurisdiction over a dispute terminates once the award is rendered?11 The drafters of Article 35 addressed two specific questions in this regard: (1) how does an arbitral tribunal retain post–award authority to render an interpretation, especially in a jurisdiction where interpretation is not expressly permitted,12 and (2) how does an interpretation become part of the award for purposes of domestic and international enforcement?13 In answer to these questions, the (p. 883) Committee concluded that, upon adoption by the parties, Article 35 served as an express agreement to extend the arbitral tribunal's jurisdiction for purposes of interpretation.14 The Committee also specified in the final version of Article 35 that an interpretation “form[s] part of the award,”15 and required that an interpretation satisfy the same technical requirements for an award established in Articles 32(2) through 32(7).16 Although not expressly required in Article 35, an arbitral tribunal is advised to render an interpretation by a majority vote pursuant to Article 31.17

Whether an interpretation is enforceable as a part of the award is ultimately determined under the governing national arbitration law. The potential difficulty in ascertaining applicable national law standards is demonstrated by the Wintershall arbitration, conducted in The Hague under the Netherlands Arbitration Act 1986 (“Dutch Act”).18 The Dutch Act authorized the arbitral tribunal to make additional awards, but was silent as to interpretations.19 After receiving the tribunal's partial award on liability, the claimants requested an interpretation or, in the alternative, an additional award to clarify the meaning of certain provisions of the underlying oil exploration agreement. Apparently unsure whether the Dutch Act barred interpretations, the tribunal decided that its interpretation also could constitute an additional award, if necessary, pursuant to Article 37 of the UNCITRAL Rules and Article 1061(3) of the Dutch Act.20

The Wintershall tribunal's approach was perhaps most prudent in light of the uncertainty as to the Dutch law. Although the tribunal's analysis of (p. 884) Dutch Law is debatable,21 an interpretation, even if not legally binding, nevertheless may usefully assist the parties in understanding and thus satisfying their obligations under the award.22 Moreover, the problem with the Wintershall award appears to have been not its ambiguity, but rather its incompleteness, a deficiency best rectified through an additional award under Article 37.23

Article 35 includes two important time limits.24 First, the parties have thirty days after receipt of the award to submit a request for interpretation. Committee representatives debated the appropriate time period. The representative of the Federal Republic of Germany proposed a three–year period, arguing that the need for interpretation typically arises at the time of execution of the award, which can be much later than the date on which the award was rendered.25 The representative of Mexico opposed a longer deadline on grounds that it would create a longer period of uncertainty for the parties.26 In the end, the Committee retained the thirty–day time limit to ensure that “the arbitrators would know reasonably quickly that some further action in respect of the award would be requested of them.”27 (p. 885) The Iran-US Claims Tribunal has adhered strictly to the thirty–day deadline.28

The second time limit requires the arbitral tribunal to render an interpretation within forty–five days of receiving a request by one or more parties. The forty–five–day time limit was designed to give the arbitrators sufficient time to take the steps necessary to interpret the award, including the commencement of new deliberations, if necessary.29 The time limit also brings finality to the award within a short period of time, by ensuring that the entire process of interpretation is concluded within approximately six weeks from the time the award was rendered. In practice, many arbitral tribunals have adhered rather strictly to the forty–five–day time limit. A notable exception is the Iran-US Claims Tribunal, whose flexibility is perhaps attributable to its unique institutional setting in which most awards do not require international enforcement but rather are paid out of the Security Account funded by Iran.30

Extracts from the Practice of the Iran-US Claims Tribunal

[Respondent] Bank Maskan also requested the Tribunal “to provide necessary interpretations” concerning that part of the Interim and Interlocutory Award which deals with interim measures.

Decisive in the counting as to when a party shall be deemed to have received the Award pursuant to the above–quoted rules is the date on which the Agent of the Government of that party has received the Award. The English text of the Award was received by the Agent of the Government of the Islamic Republic of Iran on 27 May 1985. The Farsi text of the Award was received by the Agent of the Government of the Islamic Republic of Iran on 8 August 1985. It shall be deemed to have been received also by Bank Mashan on 8 August 1985. The request for interpretation and correction filed on 13 September 1985 was thus not made within “thirty days after the receipt of the award,” as required by Articles 35 and 36. The Tribunal therefore dismisses the request for having been filed too late.

(p. 886) Component Builders, Inc. and Islamic Republic of Iran, Decision No. DEC 40–395–3 (18 Dec 1985), reprinted in 9 Iran-US CTR 404, 405 (1985–II).

As noted above, the English text of Partial Award No. 186–302–3 was received by the Agent of the Islamic Republic of Iran on 20 August 1985, and the Farsi version on 16 December 1985. Accordingly, the Civil Aviation Organization's request filed on 19 March 1986 clearly was not made within “30 days after the receipt of the Award” as required by Articles 35, 36 and 37. The Tribunal therefore dismisses the request for having been filed too late. See Component Builders, Inc. and The Islamic Republic of Iran, Decision No. DEC 40–395–3 (18 Dec. 1985); Harnischfeger Corporation and Ministry of Roads and Transportation, et al., Award No. 175–180–3 at 21–22 (26 April 1985).

International Technical Products Corp. and The Islamic Republic of Iran, Decision No. DEC 41–302–3 (16 Jun 1986), reprinted in 11 Iran-US CTR 182, 183 (1986–II)

[T]he request of Ministry of Post, Telegraph and Telephone filed on 13 June 1986 was not made within 30 days after the receipt of the Award as required by Article 35 of the Tribunal Rules and is consequently unadmissible [sic].

In view of the above, the Tribunal does not reach the question as to whether the submission could be considered a proper request for interpretation pursuant to the Tribunal Rules.

McCollough & Company and Ministry of Post, Telephone and Telegraph, Decision No. DEC 44–89–3 (7 Jul 1986), reprinted in 11 Iran-US CTR 287, 287–88 (1986–II).

[T]he Tribunal finds that the Request does not identify any ambiguity in the Award or other basis upon which an interpretation within the meaning of Article 35 can be based.

Ford Aerospace & Communications Corp., et al. and Air Force of the Islamic Republic of Iran, Decision No. DEC 47–159–3 (2 Oct 1986), reprinted in 12 Iran-US CTR 304, 305 (1986–III).

The Tribunal finds that the wording used in the Award No. 229–10173–3 exactly reproduces the language of Article III, paragraph 3 of the Claims Settlement Declaration and therefore is more appropriate than the formulation proposed by the Agent. For this reason the Tribunal (p. 887) cannot accept the opinion expressed by the Agent that the wording adopted would have the effect of altering the identity of the Claimant in Case No. 10173 which was presented pursuant to Article III, paragraph 3, of the Claims Settlement Declaration.

For the foregoing reasons, the Tribunal determines that no correction or interpretation of the Award is warranted and denies the Request.

In light of this conclusion, the Tribunal need not determine whether the Request for Correction and Interpretation is of the nature specified in Article 35 and Article 36 of the Tribunal Rules.

Picker International Corp. and Islamic Republic of Iran, Decision No. DEC 48–10173–3 (7 Oct 1986), reprinted in 12 Iran-US CTR 306, 307 (1986–II).

The Tribunal finds that while the Respondents' submission reargues certain aspects of the Case and disagrees with various conclusions of the Tribunal, it fails to point to any element of the Award that is ambiguous. The dispositif of the Award is specific and detailed. Moreover, examination of the text of the Award shows that there is no ambiguity with respect to any of the four items mentioned in the Respondents' submission. In particular, (i) the Award is clear on its face as to the denial of the Respondents' request for appointment of an expert to determine the value of the shares of the Zamzam Companies and as to the reasons for that denial …; (ii) the Award is unambiguous in determining that the Claimant was in the circumstances entitled to accelerate the Promissory Notes and quotes the explicitly interrelated provisions of paragraphs 3(f) and 4 of the Main Agreement which established that right …; (iii) the Award plainly notes that New York law governs the Loan Agreements …; and (iv) the Award sets forth the factors the Tribunal considered in determining that amount… . Thus, there is nothing in the Award that requires interpretation within the meaning of Article 35, paragraph 1, of the Tribunal Rules.

Pepsico, Inc. and Islamic Republic of Iran, Decision No. DEC 55–18–1 (19 Dec 1986), reprinted in 13 Iran-US CTR 328, 329–30 (1986–IV).

[T]he legislative history of Article 35, paragraph 1 of the UNCITRAL Arbitration Rules, to which the present Article is identical, indicates that the term “interpretation of the award” was intended to mean clarification of the award”. Thus Article 35, paragraph 1, was intended to apply only where an award contains language which is ambiguous. The dispositif of the Interim Award is specific and unambiguous. Moreover, the (p. 888) Tribunal finds no ambiguity with respect to its use of the term “status quo.” Thus, there is nothing in the Interim Award that requires interpretation within the meaning of Article 35, paragraph 1, of the Tribunal Rules.

Paul Donin de Rosiere, et al. and The Islamic Republic of Iran, Decision No. DEC 57–498–1 (10 Feb 1987), reprinted in 14 Iran-US CTR 100, 101–02 (1987–I).

Insofar as the Request allegedly seeks an interpretation of the Award, the Tribunal finds that it does not identify any aspect of the Award where the Tribunal's interpretation is necessary… . These requested interpretations largely parallel the alleged computational errors, and … would require the Tribunal to review or revise its Award. Consequently the requested interpretations fall outside the scope of Article 35.

American Bell International, Inc. and Islamic Republic of Iran, Decision No. DEC 58–48–3 (19 Mar 1987), reprinted in 14 Iran-US CTR 173, 174 (1987–I).

  1. 1.  On 6 April 1987, the Ministry of National Defence submitted a request for interpretation of certain portions of Award No. 292–353–2, pursuant to Article 35 of the Tribunal Rules.

  2. 2.  Article 35 of the Tribunal Rules provides that a request for interpretation of an award be made “within thirty days after the receipt of the award.” Furthermore, according to Article 2(3) of the Tribunal Rules, a document “shall be deemed to have been received by [the] arbitrating parties when it is received by the Agent of their Government.”

  3. 3.  The Tribunal observes that Award No. 292–353–2 was served on the Agent of the Government of the Islamic Republic of Iran on 12 February 1987. Accordingly, the request of the Ministry of National Defence filed on 6 April 1987 was not made within thirty days after the receipt of the Award as established by Article 35 of the Tribunal Rules and therefore is inadmissible.

FMC Corporation and The Ministry of National Defence, et al., Decision No. DEC 60–353–2 (27 Apr 1987), reprinted in 14 Iran-US CTR 261, 261–62 (1987–I).

The Respondents contend that the Award requires interpretation “because it does not specify whether the parties' relationship was based on the purchase or sale of goods or whether it was based on the distributorship and commission. The Respondents refer to and rely on para 21 (p. 889) of the Award, in which the Tribunal, inter alia, describes the Parties' relationship until 1978. The Tribunal notes, however, that the claim at issue does not pertain to any agreement prior to 1978. As specified in para 21 it arises out of “an agreement for the sale and purchase of certain pharmaceutical products” entered into in 1978. The sale and purchase at issue is pursuant to “Order No. 81” detailed in para 25 of the Award. The Tribunal therefore concludes that the Award does not require interpretation in this respect.

Endo Laboratories, Inc. and Islamic Republic of Iran, Decision No. DEC 74–366–3, (25 Feb 1988), reprinted in 18 Iran-US CTR 113, 113–14 (1988–I).

The Claimants' request seeks an “interpretation and correction” of paragraphs 98 and 177 of the Partial Award… . [P]aragraphs 98 and 177 are clear as to the granting of interest on the $2,948,619.50 that the Tribunal awards in the Partial Award. It is also self–evident that the jurisdiction that the Tribunal retains “over $1,564,537.36 of Uiterwyk's claim” includes jurisdiction to grant interest on that amount, in accordance with the Tribunal's practice of granting interest on claims and consistent with the awarding of interest on the other claims granted in this Case.

The Tribunal has held that Article 35, paragraph 1 was intended to apply only when an award contains ambiguous language… . Paragraphs 98 and 177 are specific and unambiguous. Accordingly, the Tribunal finds that paragraphs 98 and 177 do not require interpretation within the meaning of Article 35, paragraph 1.

Uiterwyk Corporation and Islamic Republic of Iran, Decision and Correction to Partial Award (22 Nov 1988), reprinted in 19 Iran-US CTR 171, 172–73 (1988–II).

Article 35 permits a party to request an explanation of ambiguous language contained in an Award… . Iran has pointed to no ambiguity in the Award. Moreover, its request merely repeats an argument previously made before the Tribunal. As such, the request constitutes an impermissible attempt to reargue an aspect of the Case… .

The Tribunal therefore determines that no interpretation of the Award is warranted.

Phibro Corporation and Ministry of War–Etka Co. Ltd, Decision No. DEC 97–474–3 (17 May 1991), reprinted in 26 Iran-US CTR 254, 254–55 (1991–I).

(p. 890)

  1. 1.  On 12 August 1991, the Claimant, Norman Gabay, also known as Nourollah Armanfar, timely filed a letter requesting an “interpretation” of Award No. 515–771–2 (the “Award”), filed on 10 July 1991. In the Award, the Tribunal found that the Claimant had failed to prove that his claims for the expropriation of his properties by the Respondent were outstanding on the date of the Algiers Declarations, 19 January 1981. Accordingly, the Tribunal dismissed the claims for lack of jurisdiction.

  2. 2.  In his letter, the Claimant states that

    … the most important aspect of the Award is the date of expropriation. I feel … that several key points regarding the date of expropriation and the evidence relating to those points have been overlooked in reaching the decisions on which the Award [i]s based.

    The Claimant goes on to evaluate evidence in the record that, in his opinion, would point to a finding that the taking of his properties by the Respondent occurred before 19 January 1981.

  3. 3.  The Claimant concludes by stating that “[t]his letter is not intended as a retrial, and it is solely for purposes of clarification.”

  4. 6.  Nothing in the Claimant's request falls within the scope of Articles 35, 36, or 37 of the Tribunal Rules. Article 35 permits a party to request from the Tribunal an explanation of ambiguous language contained in an Award… . The Tribunal cannot identify any ambiguous language in the Award, and the Claimant has pointed to none. Accordingly, there is nothing to interpret.

Norman Gabay and The Islamic Republic of Iran, Decision No. DEC 99–77–2 (24 Sep 1991), reprinted in 27 Iran-US CTR 194, 195 (1991–II) (citations omitted).

  1. 2.  The Tribunal finds that neither the Tribunal Rules nor its practice contemplate post–award proceedings over the merits of an award. According to the Tribunal Rules, after a final Award has been rendered, the Tribunal may only “give an interpretation of the award” (Article 35), correct “any errors in computation, any clerical or typographical errors, or any errors of similar nature” (Article 36), or “make an additional award as to claims presented in the arbitral proceedings but omitted from the award” (Article 37).

  2. 3.  Nothing in the Claimant's request falls within the scope of Articles 35, 36, or 37 of the Tribunal Rules. Indeed, the Tribunal has (p. 891) consistently held that there is no basis in the Tribunal Rules, or elsewhere, for the Tribunal to review its own awards when a party seeks to reargue the case or disagrees with the conclusions reached by the Tribunal… .

Parviz Karim–Panahi and The Government of the United States of America, Decision No. DEC 108–182–2 (27 Oct 1992), reprinted in 28 Iran-US CTR 318, 318 (1992).

  1. 1.  The Tribunal notes the Islamic Republic of Iran's “Request to Order the United States to Comply with Award No. 586–A/27–FT dated 5 June 1998,” filed on 24 July 1998 (Doc. 40) (“Request”).

  2. 2.  According to the Tribunal Rules, after a final award has been rendered, the Tribunal may “give an interpretation of the award” (Article 35), correct “any errors in computation, any clerical or typographical errors, or any errors of similar nature” (Article 36), or “make an additional award as to claims presented in the arbitral proceedings by omitted from the award” (Article 37). Westinghouse Electric Corporation and Islamic Republic of Iran, Decision No. DEC 127–389–2 (23 Apr. 1997). Iran's Request does not fall within the scope of Articles 35, 36, or 37 of the Tribunal Rules. Nothing in the Tribunal Rules provides a basis for granting the Request, which is therefore denied.

The Islamic Republic of Iran and The United States of America, Case No. A/27, Full Tribunal, Order of 5 Aug 1998, at 1.

Extracts from the Practice of NAFTA Tribunals

  1. 1.  By its Request for Interpretation, Methanex seeks from the Tribunal an interpretation of the Tribunal's Partial Award in respect of four matters:

    1. (i)  The definition of “Legally Significant Connection”, cited from Paragraph 147 of the Partial Award (page 62);

    2. (ii)  The contents and scope of the “Fresh Pleading” ordered by the Tribunal, cited from Paragraph 172(5) of the Partial Award (page 74);

    3. (iii)  The requirements of the Tribunal as to the “Evidence” to be submitted by Methanex, cited from Paragraphs 163, 164 & 165 of the Partial Award (pages 70–71); and

    4. (iv)  The nature and timetable of the “Future Proceedings”, cited from Paragraph 168 of the Partial Award (page 70).

    (p. 892)

    We shall consider each of these matters in turn, subject to a general preliminary comment.

  2. 2.  … It is well settled that such a request [under Article 35] is limited to an interpretation of the award in the form of clarification; and that it cannot extend to a request to modify or annul the award or take the form of an appeal or review of the award. Indeed, Methanex disclaims expressly any intention of “relitigating any issue the Tribunal has already decided”: see pages 1–2 of Methanex's letter.

  3. 3.  In our view, Methanex's Request does not fall within the scope of Article 35. Accordingly, we decline to treat it as such; and this response does not form part of the Partial Award. Nonetheless, it can do no harm and possibly some good if we were to address certain of the points raised by Methanex, albeit outwith Article 35 of the UNCITRAL Rules.

Letter from the Tribunal to the Parties dated 25 September 2002, paras 1–3, Methanex Corp. and The United States of America, available at http://www.state.gov/s/l/c3439.htm.

Extracts from the Practice of Ad Hoc Tribunals

  1. 4.  The Tribunal recognizes, as pointed out in Clifford Chance's Further Observations (the “Further Observations”) of May 16, 1988 that the Netherlands Arbitration Act 1986 does not provide for an interpretation of an award and that the Minister of Justice's report referred to in paragraph 11 of the Further Observations indicates that the Minister of Justice does not propose to insert in the Act the possibility of an interpretation of an award by the Tribunal. However, the Parties by their agreement of October 22, 1986, signed by duly authorized representatives of the Parties, adopted as procedural rules the UNCITRAL Rules adopted by the United Nations General Assembly on 15 December 1976, and Article 35 of these Rules provides for an interpretation of the award and Article 37 for an additional award, subject to certain notice provisions which have been fully satisfied in this case. It is the Tribunal's view that this agreement governs the arbitration since the UNCITRAL Arbitration Rules are not in conflict with any provision of the Netherlands law from which the Parties cannot derogate (Article 1–2. of the UNCITRAL Arbitration Rules) and Article 1036 of the Netherlands Arbitration Act 1986, providing that “Subject to the provisions of this Title, the arbitral proceedings shall be conducted in (p. 893) such manner as agreed between the parties …”. There is no provision in the Netherlands Arbitration Act 1986 expressly excluding the Parties from agreeing to an interpretation and their agreement under UNCITRAL Article 35 is, in the Tribunal's opinion, controlling.

    It is further the view of the Tribunal that Article 1059 of the Netherlands Arbitration Act 1986 providing for the res judicata effect of a partial award in no sense deprives the Parties of the ability to agree to an interpretation of a partial award under Article 35 of the UNCITRAL Rules. The Tribunal agrees with the Claimants that the “principle of res judicata prevents the re–opening of necessarily decided points. It does not prevent the clarification of a decision nor the giving of a decision on points which an award has left undecided.”

    The Tribunal has also noted that in his preface to the Netherlands Arbitration Act 1986, the Minister of Justice of The Netherlands, F Korthals Altes, referred to the new Act duly taking into account the Model Law on International Commercial Arbitration, adopted in 1985 by the United Nations Commission on International Trade Law (UNCITRAL), which expressly provides in Article 33 for an interpretation of an award if so agreed by the parties [Article 33(1)(b)].

    Finally, while in no sense controlling, the Respondent by recognizing in its letter of April 28, penultimate paragraph, that Article 40–4. of the UNCITRAL Rules prohibits the charging of additional fees in respect of an interpretation, in effect, recognizes that Article 35 is applicable.

  2. 5.  Nonetheless, in view of the contention by the Respondent that the Tribunal is without authority under Netherlands law to interpret its award, the Tribunal has determined whether the substance of the attached interpretation could be included in an additional award under Article 37 of the UNCITRAL and Article 1061 of the Netherlands Arbitration Act 1986, and, as required by Article 1061(3) of the Netherlands Arbitration Act 1986, the Tribunal has given to the Parties an opportunity to be heard on this question, in particular, the view of the Claimants as set forth in paragraph 14 of the Claimants' submissions of April 14, 1988 that “the inevitable and logical consequence of the Respondent's counterclaim is that claims and matters related to Article XV.3, Third Alternative, were before the Tribunal for decision.” These included clarification of how the cost recovery and production sharing principles of Article XIII of the (p. 894) EPSA apply to a non–associated Natural Gas project under the third paragraph of Article XV.3.

    It is the determination of the Tribunal that the substance of the attached interpretation could be included in an additional award under Article 37 of the UNCITRAL rules and/or Article 1061 of the Netherlands Arbitration Act 1986.

  3. 6.  The Tribunal hereby incorporates into and makes a party of this Final Award its interpretation of the Partial Award and/or additional award, issued today's date.

Wintershall AG et al. and The Government of Qatar, Final Award (Ad Hoc UNCITRAL Proceeding, 31 May 1988), reprinted in (1989) 28 ILM 834, 834–36.

  1. 6.  In summary, the Tribunal is of the view that the Claimants' application for interpretation is a request that the Tribunal should decide matters falling within the scope of the existing reference to arbitration and has determined that under Article XXXIV of EPSA a “difference or dispute” between the Respondent and Claimants arose during the hearings and exchange of submissions by the Parties concerning the interpretation of EPSA and, accordingly, it is within the Tribunal's jurisdiction to resolve this difference or dispute.

Wintershall AG, et al. and The Government of Qatar, Interpretation of Partial Award on Liability (Ad Hoc UNCITRAL Proceeding, 31 May 1988), reprinted in (1989) 28 ILM 837, 838.

Correction of the Award–Article 36

Text of the UNCITRAL Rule31

Article 36 of the UNCITRAL Rules provides:

  1. 1.  Within thirty days after the receipt of the award, either party, with notice to the other party, may request the arbitral tribunal to correct in the award any errors in computation, any clerical or typographical errors, or any errors of similar nature. The arbitral tribunal may within thirty days after the communication of the award make such corrections on its own initiative.

  2. (p. 895)
  3. 2.  Such corrections shall be in writing, and the provisions of article 32, paragraphs 2 to 7, shall apply.

Commentary

Unintentional errors, such as a misplaced decimal point or a misspelled party name, may significantly distort the intended outcome of an arbitral dispute, and possibly undermine the validity of the award. Article 36 permits the arbitral tribunal to correct computational, clerical, typographical or similar errors in an award, where necessary.

Correction is limited to the “restoration of the award's proper contents as adopted by the [arbitral tribunal].”32 Thus, Article 36 permits correction of errors in the award that the arbitral tribunal made unintentionally or heedlessly. When the Iran-US Claims Tribunal granted requests for correction under Article 36, for example, it was in large measure to correct for faulty mathematical calculations33 and typographical errors.34 “Errors of a similar nature,” also correctable under Article 36, may consist of a misspelled party's name, inaccurate dates, or mistranslations.35

The line between correction of a computational or clerical error and revision of a reasoned conclusion is seen in the Picker and Petrolane awards.36 In Picker, the respondent sought a correction of the wording used by the Tribunal to identify the claimant. In Petrolane, the Respondent sought a correction of the Tribunal's characterization of an earlier decision of the Tribunal as an “award.” In these cases, the request for correction did not involve an unintended calculation, mistake or typographical error on the part of the Tribunal. In both cases, the Tribunal understood full well the choice it had made and thus the requests were outside the scope of Article 36.

For reasons similar to those discussed above with regard to interpretation, Article 36 extends the arbitral tribunal's authority for purposes of correcting a previously rendered award, if necessary. A correction forms part of the award and thus may be enforced domestically and internationally along with (p. 896) the award.37 Accordingly, a correction should comply with Article 32(2) to (7), as required by Article 36,38 and the rule on majority voting contained in Article 31.

The arbitral tribunal's power of correction applies to “awards.” Thus, partial, interlocutory, interim and final awards are all capable of correction.39 In one unique case, the Iran-US Claims Tribunal applied Article 36 to correct not an award, but an order. The Tribunal had issued an order erroneously terminating the proceedings with respect to a certain group of claims. Without an express procedural mechanism to fix its mistake, the Tribunal, “using by analogy its power under Article 36 of the Tribunal Rules,” corrected the error and nullified the termination.40

Like other post–award mechanisms under the Rules, the correction process is not a means for revisiting the substance of the award or for reconsidering the arbitral tribunal's reasoning.41 The Iran-US Claims Tribunal, for example, found that Article 36 did not contemplate correction for alleged errors regarding “the standard of evidence applied by the Tribunal,”42 “the Tribunal's evaluation of the evidence,”43 or the Tribunal's characterization of the underlying dispute in an award of interim measures of protection.44

Two technical rules regulate the correction process. First, the party that requests correction must notify all other disputing parties of the request. Implied in this requirement is the right of the non–requesting party to comment on or contest his opponent's request for correction. Second, the correction process is subject to a thirty–day time limit; either the parties must request a correction within thirty days of receiving the award, or the arbitrators must decide sua sponte to correct the award within thirty days of its (p. 897) communication to the parties.45 In most cases, the task of assessing and correcting any technical errors in the award can be accomplished in this time frame.46

In unfortunate circumstances, a party might attempt to abuse the correction process for purposes of delaying or disrupting the arbitral proceedings. The thirty–day time limits established in Article 36 provide ways of minimizing the potential for dilatory tactics.47 Another perhaps more effective safeguard is the arbitrators' inherent discretion to determine whether to apply the correction process. As the commentary on the Revised Draft explains:

Even in cases where the arbitrators receive a timely request from one or both of the parties that an error in the award is corrected, the arbitrators have full discretion to decide whether or not they wish to issue such a correction (e.g. the arbitrators may decide that the alleged error whose correction was requested was not an error at all).48

Similarly, the arbitral tribunal has authority to decide against correction if an error is genuine but has no material impact on the validity of the award.

The Iran-US Claims Tribunal has established a useful practice for correcting an award. When applying Article 36, the Tribunal typically issues a (p. 898) “Correction to Award,” which sets forth its decision on each of the alleged errors at issue. Appended to the “Correction to Award” are the corrected pages of the award for the parties' files and a signature page that includes the signatures of at least a majority of the arbitrators in favor of the correction.49 The “Correction to Award” is dated, but that date has no legal effect on the original date of the award, which remains the date of the signing of the award.50

Extracts from the Practice of the Iran-US Claims Tribunal

(1)  Request for correction granted

Pursuant to Article 36 of the Tribunal Rules, the Tribunal hereby corrects Award No. 93–2–3 as follows:

The Terms “Two Million Eight Hundred and Fifty Seven Thousand One Hundred and Fifty Three United States Dollars (U.S. $2,857, 153)” appearing on page 23 of the Award are corrected to read “Two Million Eight Hundred and Fifty Seven Thousand One Hundred and Forty Three United States Dollars (U.S. $2,857, 143)”.

American International Group, Inc. and Islamic Republic of Iran, Award No. 93–2–3 (19 Dec 1983), reprinted in 4 Iran-US CTR 96, 111 (1983–II).

The Respondents first note that there is a discrepancy between the amount awarded for “per diem rental” in paragraphs 101 and 102 of the Partial Award and the figure in paragraphs 189 and IV(i). The Tribunal determines that this is due to a typographical error. The amount awarded for “per diem rental” should be corrected, pursuant to Article 36, paragraph 1 of the Tribunal Rules.

Second, the Respondents note that in paragraph 189 the total amount awarded the Claimant does not correspond to the sum of the amounts referred to in earlier paragraphs of the Partial Award. The Tribunal determines that this is the result of an error in computation that should be corrected pursuant to Article 36, paragraph 1 of the Tribunal Rules.

Third, the Respondents point out that the amount due Uiterwyk with respect to Sea–Man–Pak bonds was included in the Award against Iran Express Lines as well as in the Award against Sea–Man–Pak. The Tribunal determines that this is due to an error in computation and should (p. 899) be corrected pursuant to Article 36, paragraph 1 of the Tribunal Rules… .

Taking into account the cumulative effect of the corrections referred to [in] this Decision, Iran Express Lines is obligated to pay Uiterwyk U.S. $16,244,770.23, plus interest… .

Uiterwyk Corporation and Islamic Republic of Iran, Decision No. DEC 96–381–1 (22 Nov 1988), reprinted in 19 Iran-US CTR 171, 173–74 (1988–II).

As to the request for correction of allegedly inconsistent dates of Persian and English versions of the Award, the Tribunal notes that there is no such inconsistency. The Gregorian and Persian dates in line 3 of page 7 of the Persian version of the Award have been inadvertently switched. The Tribunal notes that Article 36, paragraph 1, of the Tribunal Rules provides for the correction of “errors in computation, any clerical or typographical errors, or any errors of similar nature.” The Tribunal further notes that the request for correction of the error in the Persian version of the Award falls within the scope of Article 36, paragraph 1, of the Tribunal Rules.

Control Data Corporation and Islamic Republic of Iran, Decision No. DEC 86–88–3 (30 Jun 1989), reprinted in 22 Iran-US CTR 151, 153 (1989–II).

  1. 4.  … As to Dr. Rassekh's letter, described by the Award as “undated,” the Tribunal notes that in the English translation submitted by the Respondents the letter is undated, and that the date provided in the Persian text is not legible. In response to Bimeh Iran's request, the Tribunal deems it proper to delete the term “undated” from the letter's description provided in paragraph 175 of the Award. To this extent, therefore, the Tribunal grants Bimeh Iran's request in accordance with Article 36 of the Tribunal Rules.

Component Builders, Inc. and Islamic Republic of Iran, Correction to Award No. 431–395–3 (2 Feb 1990), reprinted in 23 Iran-US CTR 122, 123, 125 (1989–III).

The Tribunal has come across a mathematical error in paragraph 97 of the Award in this Case filed on 6 July 1993. The error in question is the following.

The amount stated in paragraph 97 of the Award as the value of those AFFA assets discussed in paragraphs 53 through 96 of the Award was 1,084,175,345 rials. It should have read 1,100,253,669 rials.

(p. 900)

The correction of this error affects a number of figures used in the computation of the amount awarded. Consequently, in accordance with Article 36, paragraph 1, of the Tribunal Rules, the Tribunal makes the following corrections to its Award No. 549–967–2. Copies of the corrected pages are attached.

1.  Paragraph 97

In the second line of paragraph 97, the figure “1,084,175,345 rials” is replaced with “1,100,253,669 rials.”

In the sixth line of paragraph 97, the figure “1,241,675, 122 rials” is replaced by “1,257,753,446 rials.”

[Other corrections omitted]

Harold Birnbaum and The Islamic Republic of Iran, Correction to Award No. 549–967–2 (19 Jul 1993) (footnote omitted).

The following corrections of a typographical nature are hereby made to the English version of Award No. 580–832–3, filed on 23 April 1997.

On page 5, in the Table of Contents, the paragraph number for the commencement of the section on “Interest” is “250”, not “225.”

In paragraph 192, line 8, the figure “U.S. $200,000” is deleted and is replaced by the figure “U.S. $2,000,000.”

A copy of the corrected page is attached.

Vivian May Tavakoli and Islamic Republic of Iran, Correction to Award No. 580–832–3 (16 Jun 1997).

(2)  Request for correction denied

… Respondent Bank Maskan filed a document … in which the said Respondent asked that the Award be corrected in so far as regards its section on “Procedural History” and the Tribunal's findings concerning Claimant's nationality… .

Decisive in the counting as to when a party shall be deemed to have received the Award pursuant to the above–quoted rules is the date on which the Agent of the Government of that party has received the Award. The English text of the Award was received by the Agent of the Government of the Islamic Republic of Iran on 27 May 1985. The Farsi text of the Award was received by the Agent of the Government of the Islamic Republic of Iran on 8 August 1985. It shall be deemed to have been received also by Bank Mashan on 8 August 1985. The request for (p. 901) interpretation and correction filed on 13 September 1985 was thus not made within “thirty days after the receipt of the award,” as required by Articles 35 and 36. The Tribunal therefore dismisses the request for having been filed too late.

Component Builders, Inc. and Islamic Republic of Iran, Decision No. DEC 40–395–3 (18 Dec 1985), reprinted in 9 Iran-US CTR 404, 404–05 (1985–II).

By Order of 24 July 1985, the Tribunal advised the Parties that it intended to terminate this Case pursuant to its Decision in Case No. A/17 unless the Claimant, by 2 September 1985, informed the Tribunal that the Claim involved amounts owing and payable from Dollar Account No. 2. This deadline was subsequently extended to 1 October 1985.

On 1 October 1985 Claimant filed two letters. In one, Claimant requested a further two month extension of time to submit its response to the Tribunal's Order of 24 July 1985; in the other, Claimant responded to that Order, stating that the Claim did not involve amounts owing and payable to it from the Dollar Account No. 2.

The Tribunal notes its Orders filed on 9 October 1985 and 26 November 1985, respectively granting the extension requested in the one letter and terminating the Case in response to the other letter.

The Tribunal also notes the letter filed on 29 November 1985 by the Agent of the Islamic Republic of Iran, requesting correction of the Tribunal's Order of 26 November 1985 terminating the arbitral proceedings in this Case, on the ground that such termination was erroneous in view of the Tribunal's Order of 9 October 1985 granting an extension and requesting a further extension of three months to answer the Tribunal's Order of 24 July 1985. The Tribunal also notes Respondent's letters of 14 January 1986 urging the Chamber to adhere to that Order.

The Tribunal further notes the letter filed on 30 December 1985 by the Agent of the Islamic Republic of Iran, apparently reversing one of Claimant's 1 October 1985 letters, stating that the claims set forth in schedule B to Claimant's Statement of Claim and denominated “Interest Only Claims” are payable out of Dollar Account No. 2 and urging that the Tribunal has jurisdiction regarding that portion of this Case.

In view of the above–mentioned circumstances and in order to avoid any prejudice to the Claimant, the Tribunal using by analogy its power under Article 36 of the Tribunal Rules, hereby corrects its order of (p. 902) 26 November 1985 so as to reinstate that portion of this Case which is related to schedule B entitled “Interest Only Claims,” attached to Claimant's Statement of Claim. Such reimbursement will enable the Tribunal to clarify whether it has jurisdiction over the schedule B “Interest Only Claims.”

The Claimant is hereby instructed to file a supplemental brief not later than 20 April 1986, detailing its schedule “Interest Only Claims” and explaining why it believes such Claims are payable from Dollar Account No. 2. The Respondent shall file its comments thereto by 20 July 1986.

Bank Markazi Iran and European American Banking Corporation, Case No. 679, Chamber Two, Order of 22 Jan 1986.

The Tribunal finds that the wording used in the Award No. 229–10173–3 exactly reproduces the language of Article III, paragraph 3 of the Claims Settlement Declaration and therefore is more appropriate than the formulation proposed by the Agent. For this reason the Tribunal cannot accept the opinion expressed by the Agent that the wording adopted would have the effect of altering the identity of the Claimant in Case No. 10173 which was presented pursuant to Article III, paragraph 3, of the Claims Settlement Declaration.

For the foregoing reasons, the Tribunal determines that no correction or interpretation of the Award is warranted and denies the Request.

In light of this conclusion, the Tribunal need not determine whether the Request for Correction and Interpretation is of the nature specified in Article 35 and Article 36 of the Tribunal Rules.

Picker International Corporation and Islamic Republic of Iran, Decision No. DEC 48–10173–3 (7 Oct 1986), reprinted in 12 Iran-US CTR 306, 307 (1986–II).

First, the Request argues that the Tribunal in paragraph 9 of its Interim Award mischaracterized the nature of the underlying dispute between the Parties and seeks a “correction” of this alleged mischaracterization… .

As to the request for a “correction” of paragraph 9 of the Interim Award, the Tribunal notes that the Interim Award contains no finding by the Tribunal as to the actual nature of the underlying dispute. Further, Article 36, paragraph 1, of the Tribunal Rules provides only for the correction of “errors in computation, any clerical or typographical errors, or any errors of a similar nature”. The Tribunal finds that the present (p. 903) request for a “correction” does not fall within the scope of Article 36, paragraph 1, of the Tribunal Rules, and therefore denies this request.

Paul Donin de Rosiere and Islamic Republic of Iran, Decision No. DEC 57–498–1 (10 Feb 1987), reprinted in 14 Iran-US CTR 100, 101 (1987–I).

Insofar as the Request allegedly seeks the correction of computational errors in the provisions of the Award, the Tribunal finds that Respondents have identified no such errors. Rather they have submitted an elaborate reargumentation based on the evidentiary record aiming at the reconsideration and revision of some of the findings on the basis of which computations are made in the Award. Such a request does not fall within the scope of Article 36.

American Bell International Inc. and Islamic Republic of Iran, Decision No. DEC 58–48–3 (19 Mar 1987), reprinted in 14 Iran-US CTR 173, 173–74 (1987–I).

  1. 2.  The Request for a “review and correction” concerns “certain of the calculations” in the Award. Article 36 permits corrections only of “any errors in computations, any clerical or typographical errors, or any errors of similar nature.” The basis of the Claimant's request is its disagreement with the Tribunal's approach to determining certain elements of the Claimant's claim for performance. The Award states that the Tribunal adopted its approach “[a]fter careful consideration of various options” … and then explains its reasoning in considerable detail. The Claimant here seeks a revision of the Tribunal's reasoned findings, not a mere correction of an arithmetic error. The provisions of Article 36 do not apply in such a circumstance.

Harris International Telecommunications, Inc. and Islamic Republic of Iran, Decision No. DEC 73–409–1 (26 Jan 1988), reprinted in 18 Iran-US CTR 76, 76 (1988–I).

The Respondents also take issue with the Award on several matters of substance and base thereon several requests for correction. These include a) a request for the Tribunal to correct its alleged failure to take into account in the Respondents' favor gratis samples amounting to 10% of the ordered amount; b) a request for the Tribunal to correct its findings in paragraph 57(b) for which, according to the Respondents, no evidentiary basis exists; c) a request for the Tribunal to apply a 30% credit due (p. 904) the Respondents on account of commission, as opposed to a 25% credit, on the grounds that the Claimant had applied a 30% credit throughout the course of the relationship; d) a request that the Tribunal decrease the total sum awarded by the amount of the clearance charges; and finally e) a request that the Tribunal not award interest in this Case.

The Tribunal notes that Article 36 of the Tribunal Rules authorizes the Tribunal solely to correct “any errors in computation, any clerical or typographical errors or any errors of similar nature”. The Tribunal finds that none of the Respondents' requested corrections falls within the parameters of Article 36.

Endo Laboratories, Inc. and Islamic Republic of Iran, Decision No. DEC 74–366–3 (25 Feb 1988), reprinted in 18 Iran-US CTR 113, 114 (1988–I).

  1. 4.  IACA's requests … relate to the dates selected in paragraphs 135, 136 and 139 of the Partial Award for calculating interest on various elements of the award made to both the Claimant and the Respondents. The rationale for choosing the relevant dates is explained fully in the Partial Award and the Tribunal note that there is no inaccuracy in any of paragraphs 135, 136 and 139… . The Tribunal finds that the request to change the dates from which interest is awarded does not fall within the scope of Article 36, paragraph 1. The Tribunal therefore denies this portion of the Request.

  2. 5.  Although IACI has not specified clearly the nature of the alleged errors in the figures in paragraph 2 of the Partial Award, the Tribunal notes certain inconsistencies in the figures recited in this paragraph with those elsewhere in the Partial Award. The Tribunal determines that paragraph 2 of the Partial Award contains a clerical error which should be corrected, pursuant to Article 36, paragraph 1 of the Tribunal Rules.

Avco Corporation and Iran Aircraft Industries, Decision and Correction to Partial Award, Award No. 377–261–3 (13 Jan 1989), reprinted in 19 Iran-US CTR 253, 254–55 (1988–II).

In his letter, the Agent asserts that a citation in paragraph 50 of the Award to Phillips Petroleum Company Iran v. Islamic Republic of Iran, et al., Award No. 425–39–2 (29 June 1989), is an incorrect citation because the parties in the Phillips Case had agreed in their subsequent Settlement Agreement that the English version of that Award … shall “be deemed by the Parties as null and void and of no effect whatsoever”. (p. 905) The Agent submits that this request should be dealt with as a request to correct a clerical error pursuant to Article 36 of the Tribunal Rules of Procedure… .

The objection to a citation of an Award on the grounds raised by the Agent's letter does not, in the view of the Tribunal, constitute a request for correction of an error within the meaning of Article 36 of the Tribunal Rules. The citation was correct and was to an Award rendered by the Tribunal, albeit one rendered in English only. While the parties in their subsequent settlement agreed that they would deem that Award null and void upon the issuance of an Award on Agreed Terms giving effect to their Settlement Agreement, that cannot alter the fact that Award 425 was rendered in English and stated the conclusions and reasoning of the Tribunal. As such, the subsequent citation of that Award cannot be considered erroneous.

Petrolane, Inc. and Islamic Republic of Iran, Decision No. DEC 101–131–2 (25 Nov 1991), reprinted in 27 Iran-US CTR 264, 264–65 (1991–II).

  1. 3.  [Respondent] Bimeh Iran first points out that it was entitled to rely on Article 36 of the Iranian Insurance Law relating to the statute of limitations, and that the Tribunal should have requested the text of this Article if required for its decision. On this issue, the Award states, inter alia, that “Bimeh Iran has not submitted in evidence the text of the Iranian Insurance Law upon which it bases its defence. Accordingly, this defence is dismissed for lack of evidence and so the Tribunal need not consider whether such limitation was subsequently nullified.” Bimeh Iran's request, while taking issue with the standard of evidence applied by the Tribunal fails to identify an error of the kind contemplated by Article 36 of the Tribunal Rules. Consequently, this part of Bimeh Iran's request does not fall within the scope of this Article.

  2. 4.  Bimeh Iran's second comment is that “Claimants' assertion that Dr. Rasekh re–inspected the workshop on 5 December 1978 (14 Azar 1357) is not true and not supported by evidence… .” As to the re–inspection, this is a matter of the Tribunal's evalution of the evidence… . This part of Bimeh Iran's request is therefore outside the scope of Article 36 of the Tribunal Rules… .

Component Builders, Inc., et al. and The Islamic Republic of Iran, et al., Correction to Award 431–395–3 (2 Feb 1990), reprinted in 23 Iran-US CTR 122, 122–23 (1989–III).

(p. 906)

  1. 10.  The correction in an award of “any errors in computation, any clerical or typographical errors, or any errors of similar nature,” provided for by Article 36 of the Tribunal Rules, does not constitute any revision of the award, in the sense of a change in a substantive holding. The correction under Article 36 is simply an elimination of what in law does not form part of the award; it is a restoration of the award's proper contents as adopted by the Tribunal. The deadlines are tight: thirty days after the receipt of the award for a correction request by a Party and, equally, thirty days after the communication of the award for a correction of the award by the Tribunal on its own initiative.

Harold Birnbaum and The Islamic Republic of Iran, Decision No. DEC 124–967–2 (14 Dec 1995), reprinted in 31 Iran-US CTR 286, 288 (1995).

  1. 2.  On 4 August 1995, the Claimant submitted a request for correction (the “request”) of the Award pursuant to Article 36, paragraph 1, of the Tribunal Rules. In the request, the Claimant contends that the 8 percent interest rate used by the Tribunal, in paragraph 112 of the Award, “must be the result of a calculation, typographical or similar error.”

  2. 10.  Were the 8 percent rate employed by the Tribunal in paragraph 112 of the Award the result of an error envisioned by Article 36, paragraph 1, of the Tribunal Rules, the Tribunal would not hesitate to correct the error. See Birnbaum, Correction to Award No. 549–967–2 (19 July 1993). Such a computational error, however, did not occur in this Case.

  3. 11.  The Tribunal was fully aware of the consequences of its choice, and, considering the evidence and arguments submitted in the present claim, determined that an 8 percent rate of interest fairly compensated the Claimant for damages suffered due to delayed payment. The difference from the rate of interest awarded by the Tribunal in Birnbaum did not result from an error in calculation or otherwise and is consequently not subject to correction pursuant to Article 36 of the Tribunal Rules.

Fereydoon Ghaffari and The Islamic Republic of Iran, Decision No. DEC 123–968–2 (30 Oct 1995), reprinted in 31 Iran-US CTR 124, 124–25 (1995).

(p. 907)

Article 36 of the Tribunal Rules allows the correction in an award of “any errors in computation, any clerical or typographical errors, or any errors of similar nature.” The Tribunal has previously held that the type of correction envisaged by this provision “does not constitute any revision of the award, in the sense of a change in a substantive holding” and that it simply provides for “an elimination of what in law does not form part of the award; it is a restoration of the award's proper contents as adopted by the Tribunal.” … Efforts to reargue certain aspects of a case or to review conclusions in awards rendered by the Tribunal find no basis in the Tribunal Rules… .

The Tribunal has examined the Award, in particular, the figures and calculations used to compute the amount payable to the United States. No error in computation or error of a similar nature has been detected. For this reason, the Tribunal denies the request in so far as it is based on Article 36 of the Tribunal Rules.

United States and Islamic Republic of Iran, Decision No. DEC 126–B36–2 (17 Mar 1997), reprinted in 33 Iran-US CTR 56, 58 (1997).

  1. 1.  The Tribunal notes the Islamic Republic of Iran's “Request to Order the United States to Comply with Award No. 586–A/27–FT dated 5 June 1998,” filed on 24 July 1998 (Doc. 40) (“Request”).

  2. 2.  According to the Tribunal Rules, after a final award has been rendered, the Tribunal may “give an interpretation of the award” (Article 35), correct “any errors in computation, any clerical or typographical errors, or any errors of similar nature” (Article 36), or “make an additional award as to claims presented in the arbitral proceedings but omitted from the award” (Article 37). Westinghouse Electric Corporation and Islamic Republic of Iran, Decision No. DEC 127–389–2 (23 Apr. 1997). Iran's Request does not fall within the scope of Articles 35, 36, or 37 of the Tribunal Rules. Nothing in the Tribunal Rules provides a basis for granting the Request, which is therefore denied.

The Islamic Republic of Iran and The United States of America, Case No. A27, Full Tribunal, Order of 5 Aug 1998, at 1.

(p. 908) Additional Award–Article 37

Text of the UNCITRAL Rule51

Article 37 of the UNCITRAL Rules provides:

  1. 1.  Within thirty days after the receipt of the award, either party, with notice to the other party, may request the arbitral tribunal to make an additional award as to claims presented in the arbitral proceedings but omitted from the award.

  2. 2.  If the arbitral tribunal considers the request for an additional award to be justified and considers that the omission can be rectified without any further hearings or evidence, it shall complete its award within sixty days after the receipt of the request.

  3. 3.  When an additional award is made, the provisions of article 32, paragraphs 2 to 7, shall apply.

Commentary

Article 37 authorizes the arbitral tribunal to make an additional award “as to claims presented in the arbitral proceedings but omitted from the award.” The UNCITRAL drafters observed that in most jurisdictions an award that failed to address all the claims raised in arbitration would not be recognized or enforced.52 Article 37 thus provides the arbitrators a mechanism for completing their mandate, when necessary, by making an additional award that resolves all remaining claims.53 As the travaux préparatoire note, in the absence of such a provision, “a lengthy, costly arbitration might be totally invalidated because the arbitrators inadvertently failed to rule in their award on each part of every claim raised during the arbitral proceedings.”54

The drafters intended Article 37 to serve as an express agreement by the parties to extend the arbitrators' jurisdiction over the dispute to make an additional award.55 Such agreement may or may not be necessary in practice depending on the requirements of the applicable national arbitration law. In some jurisdictions, an award that fails to address all claims is not a final award; thus the arbitral tribunal's jurisdiction over the dispute remains in (p. 909) force until all outstanding claims are resolved.56 Nevertheless, an additional award is an “award” within the meaning of the Rules and thus should comply with Article 32(2) through 32(7), as required by Article 37, and the rule on majority voting contained in Article 31.57

Professor Sanders observed during Committee negotiations that Article 37 was intended to cover “obvious cases of omission” in which the arbitrators failed to render a complete award.58 Examples of such cases may include when the arbitrators have failed to fix or apportion the costs of arbitration,59 rule on a claim for interest payments, or adjudicate in the award a counter–claim that was asserted without substantial supporting evidence.60 As noted in Committee discussions, Article 37 obviously has no effect in cases of deliberate omission where an arbitral tribunal has for specific reasons intentionally chosen not to address a claim or issue in the award.61 Nevertheless, to avoid any misunderstandings, it is good practice for an arbitral tribunal to document in the award the disposition of each of the parties' respective claims, no matter how small or inconsequential their bearing is on the outcome of the case.

Article 37(2) grants the arbitral tribunal wide discretion to determine if a request for an additional award is “justified.”62 The arbitrators, for example, may reject a request on grounds that there was no omission of claims,63 that (p. 910) the award sufficiently addressed the alleged omissions,64 and that the party's request generally falls outside the scope of Article 37.65 The arbitrators have no express authority to make additional awards sua sponte, although arguably they must inform the parties of the discovery of any important omissions as part of their general duty to ensure that validity and enforceability of the award.66

Article 37 imposes two notable limitations on the arbitral tribunal's power to complete the award. First, an additional award may address only “claims presented in the arbitral proceedings.” Thus, the arbitrators are not authorized to make an additional award to address a claim that was not raised legitimately in the parties' written submissions or at the hearing, even if the parties jointly request such action. If further arbitration is required on new or related issues, the parties must initiate a new arbitration.

The second limitation is that the arbitral tribunal can make additional awards only if the omitted claim can be redressed “without any further hearing or evidence.”67 This limitation was the subject of intense debate in Committee negotiations. The representative of the Soviet Union opposed the clause. He argued that if the arbitrators were to blame for not addressing the omitted claim or taking the necessary evidence, it would be unfair to require the parties to initiate a new arbitration to resolve the remaining claims.68 On the other side, the representative of the Federal Republic of Germany observed that without the clause parties might abuse the completion process by attempting to present new claims.69 The Committee retained the clause, concluding that any downsides would be offset by the parties' right, pursuant to Article 29, to reopen the hearings in certain cases.70

The Commission's position on the permissibility of further hearings and evidence to complete an award changed notably in drafting the Model Law. Article 33(3) of the Model Law, which is virtually identical to Article 37 of the Rules in all other respects, omits the limiting clause “without any further hearing or evidence.”71 The change was made because UNCITRAL recognized that without the ability to gather additional evidence to address an (p. 911) omission in an award, the entire award could be nullified in set aside proceedings.72 The parties to a dispute accordingly may wish to modify Article 37 of the Rules to conform to Article 33(3) of the Model Law.73

The process for completing an award under Article 37 is subject to two time limits.74 First, a party has thirty days after receipt of the award to submit a request for an additional award.75 Second, if the arbitral tribunal chooses to grant a party's request, it has sixty days from the date of receipt of the request to render the additional award.76

Extracts from the practice of the Iran-US Claims Tribunal

(1)  Request for additional award granted

Applying the provisions set out in Article 37 of the Tribunal Rules and since the Tribunal has omitted to render a decision regarding the request for costs, the Tribunal decides that the Claimant, Assistance in Development Educational System, Inc., is obligated to pay costs to Respondent the National Defence Industries Organization in the sum of US $4,000.00.

Assistance in Developing Educational System, Inc. and Islamic Republic of Iran, Case No. 218, Chamber One, Order of 31 Oct 1983.

(2)  Request for additional award denied

The Tribunal has determined that no portion of the claim or counterclaim has been omitted from the above Award so as to warrant an additional award as requested by AEOI.

Woodward–Clyde Consultants and Islamic Republic of Iran, Case No. 67, Chamber Three, Order of 30 Dec 1983.

Interpreting Article 37 to give full effect to its purpose, the Tribunal decides that the date of “receipt of the award” is the date that the Award in that party's language is served upon the Agent of the relevant State–Party. Likewise the Tribunal decides that for the purpose of meeting the 30–day limitation, the date the “request” is made is the date that the (p. 912) requesting submission, even if in only one language, is received. Such request may not be filed or acted upon, however, until the other language version is received and such other version must be received within a reasonable period. See, Article 17, Tribunal Rules

In the present case the English version of the Request for additional award was received on 13 August 1984, less than 30 days after receipt of the Award by the Agents for the United States. Moreover, the Farsi version of the request was received in a timely fashion thereafter. Therefore, the request for additional award in the instant case was made in a timely manner.

Hood Corporation and Islamic Republic of Iran, Decision No. DEC 34–100–3 (1 Mar 1985), reprinted in 8 Iran-US CTR 53, 54 (1985–I).

As noted, Article 37, paragraph 1, of the Tribunal Rules permits an additional award only with respect to “claims presented in the arbitral proceeding but omitted from the award.” The record in this Case, as described above, leaves no doubt that no claims were omitted from the Award, for all of the claims were directed solely against the Government and all were explicitly decided by the Tribunal. Accordingly, there is no basis for an additional award under the Tribunal Rules.

Flexi–Van Leasing, Inc. and Islamic Republic of Iran, Decision No. DEC 54–36–1 (18 Dec 1986), reprinted in 13 Iran-US CTR 325, 327 (1986–IV).

… the Tribunal Rules permit an additional award only with respect to “claims presented in the arbitral proceedings but omitted from the award”. The record in this Case, as described above, leaves no doubt that no claims or counterclaims were omitted from the Final Award. Accordingly, the Tribunal concludes that the request for an additional award is not justified.

International Schools Services, Inc. and Islamic Republic of Iran, Decision No. DEC 61–123–1 (28 Apr 1987), reprinted in 14 Iran-US CTR 279, 281 (1987–I).

The Agent of the Government of the Islamic Republic of Iran on behalf of the Respondent Bank Markazi Iran (“Bank Markazi”), stated in the Request that “legal damages, including, inter alia, damages arising out of preparing briefs and attending hearings which relief was sought … should have been awarded to Bank Markazi Iran.”

The Tribunal notes that, pursuant to Article 38, paragraph 1 of the (p. 913) Tribunal Rules, Paragraph 71(g) of the Award disposes of the claim referred to by Bank Markazi.

The Tribunal concludes that it did not omit in the Award any claims presented in the arbitral proceedings in this Case and therefore the Award does not warrant any additional consideration.

Exxon Research and Engineering Company and Islamic Republic of Iran, Decision No. DEC 63–155–3 (29 Jul 1987), reprinted in 16 Iran-US CTR 110, 111 (1987–III).

[T]he Tribunal notes that Article 37 of the Tribunal Rules permits a party to make a request for an additional award only “as to claims presented in the arbitral proceedings but omitted from the award”. The subject matter of this request was not omitted from the award, but is discussed in detail in paragraphs 177 through 181 and is also referred to in the dispositif… . The Tribunal, therefore, finds that there is no basis under the Tribunal Rules for making the additional award requested.

Harris International Telecommunications, Inc. and Islamic Republic of Iran, Decision No. DEC 73–409–1 (26 Jan 1988), reprinted in 18 Iran-US CTR 76, 77 (1986–IV).

[W]hile the Request falls, prima facie, within the scope of Article 37, the Tribunal cannot agree that a claim which was presented in the arbitral proceedings was omitted from the Award. The Award specifically addressed the Claimants' contention that their dominant and effective nationality during the relevant period from the date the Claim arose to 19 January 1981 was that of the United States; indeed, it was expressly restricted to that issue. Consequently, the Tribunal finds that there is no omission to be rectified in the Award.

Reza and Shahnaz Mohajer–Shojaee and Islamic Republic of Iran, Decision No. DEC 95–273–1 (26 Dec 1990), reprinted in 25 Iran-US CTR 273, 274 (1990–II).

In his letter the Claimant asserts that “[t]he Tribunal has not considered other claims of the Claimant, namely the ownership of his late father of the buildings and improvements up to the date of his death in 1979… .”

[T]he Tribunal cannot agree that the Claimant presented a claim which was omitted from the Award. The Award in its dispositif … dismissed all claims of the Claimant. It dismissed the claim based on the alleged expropriation of the buildings and improvements on the land after (p. 914) determining that the Claimant did not have ownership interests in either the land or the buildings and improvements on the land after 1975, when both land and such fixtures had been transferred to NPIC, as stated in the parts dealing with Facts and Contentions and Reasons for the Award… . Moreover, … the Tribunal dismissed any claim for personal property left on the farm. Accordingly, in the present Case there is no basis for an additional Award under the Tribunal Rules.

Esahak Saboonchian and Islamic Republic of Iran, Decision No. DEC 103–313–2 (13 Feb 1992), reprinted in 28 Iran-US CTR 51, 51–52 (1992).

  1. 1.  The Tribunal notes the Islamic Republic of Iran's “Request to Order the United States to Comply with Award No. 586–A/27–FT dated 5 June 1998,” filed on 24 July 1998 (Doc. 40) (“Request”).

  2. 2.  According to the Tribunal Rules, after a final award has been rendered, the Tribunal may “give an interpretation of the award” (Article 35), correct “any errors in computation, any clerical or typographical errors, or any errors of similar nature” (Article 36), or “make an additional award as to claims presented in the arbitral proceedings but omitted from the award” (Article 37). Westinghouse Electric Corporation and Islamic Republic of Iran, Decision No. DEC 127–389–2 (23 Apr. 1997). Iran's Request does not fall within the scope of Articles 35, 36, or 37 of the Tribunal Rules. Nothing in the Tribunal Rules provides a basis for granting the Request, which is therefore denied.

The Islamic Republic of Iran and The United States of America, Case No. A/27, Full Tribunal, Order of 5 Aug 1998, at 1.

The Finality of Awards and the Inherent Power to Reconsider

Commentary

A debatable point with long lineage is an international arbitration panel's inherent power to reconsider its award in the face of alleged due process or public policy violations; typically fraud. The UNCITRAL Rules, like most arbitral rules, provide no explicit authority to the panel to reconsider its award.77 Article 32(2) provides that an award is “final and binding” and “the parties undertake to carry out the award without delay.”78 Articles 35, 36 and (p. 915) 37, as discussed above, invest the panel with only limited jurisdiction to interpret, correct and supplement the award. Therefore, absent inherent power for the panel to reconsider an award, an unhappy party must turn to a national court under the relevant arbitration laws.79

The key to approaching this debate is found in the nature of inherent powers. Articles 35, 36 and 37 are examples of explicit powers given to the Tribunal. Implied powers could be read into a certain set of arbitration rules, but also could be expressly denied the tribunal. Inherent powers, however, imply something more than implied powers. Something inherent is something necessarily a part of the object in question. Inherent powers in this sense are those powers that are not explicitly granted to the tribunal but must be seen as a necessary consequence of the parties' fundamental intent to create an institution with a judicial nature. Inherent powers may be limited or denied by the parties, but the more such powers are necessary to the judicial nature of the tribunal, then the more strictly the limitation or denial is construed so as to preserve the overall intention of the parties. The debate then becomes precisely what powers are necessary for an institution to possess a judicial nature.

Two further points must now be added. First, much of the long lineage of inherent powers comes from interstate arbitration. One should not simply assume that the interstate precedents are applicable to the international commercial arbitration context. As a process, interstate arbitration differs from international commercial arbitration in that it is not envisioned that interstate arbitration will be subject to review in national courts. The entire international commercial arbitration process, unless there is settlement, in contrast involves an arbitration followed by certain procedures before national courts. It is true that the lineage regarding inherent powers now extends into the international commercial arbitration field. In an ad hoc arbitration under the UNCITRAL Rules, one distinguished panel (Judge Stephen M Schwebel, Professor Don Wallace, and Monroe Leigh, Esq.) found:

Nevertheless, a court or Tribunal, including this international arbitral Tribunal, has an inherent power to take cognizance of credible evidence, timely placed before it, that its previous determinations were the (p. 916) product of false testimony, forged documents or other egregious “fraud on the Tribunal.” [Cites to interstate arbitrations decisions deleted.] Certainly if such corruption or fraud in the evidence would justify an international or a national court in voiding or refusing to enforce the award, this Tribunal also, so long as it still has jurisdiction over the dispute, can take necessary corrective action. See the Statute of the International Court of Justice, Art. 61 (permitting revision of an award upon the subsequent discovery of a new decisive fact); ICSID Convention Art. 51 (same); US Arbitration Act, 9 USC Sect. 10 (permitting judicial annulment of an arbitral award “procured by corruption, fraud or undue means”).

The present Tribunal would not hesitate to reconsider and modify its earlier award were it shown by credible evidence that it had been the victim of fraud and that its determinations in the previous award were the product of false testimony. However, no such evidence has been adduced. As in many complex cases, this Tribunal has been required to weigh and resolve occasional inconsistencies in the evidence of both sides in this arbitration, and to come to its best determination of the relevant facts. Nevertheless, the Tribunal is satisfied that the material facts on which it based its previous award on jurisdiction and liability, as well as the present award on damages and costs, are sufficiently explained and proved by credible evidence.80

As appears almost always to be the case, the arbitrators acknowledge an abstract authority to reopen awards in the face of severe misconduct by the winning party, but do so in cases where such misconduct does not exist.

One must ask, however, why the existence of a power in national courts to void or to refuse to enforce an award “certainly” means that the arbitral panel also has that power. Indeed, the opposite conclusion is suggested by the second point to be made: The notion of inherent powers could be easily abused. It is a sense of necessity that justifies a tribunal invoking inherent powers; it is the sense of necessity that allows the acceptance of such powers by the parties. Together these two points suggest that it may not be necessary for an international commercial arbitration panel to invoke an inherent power if that necessary part of the whole process is available in either the courts of the place of arbitration or the place where enforcement is sought.81

(p. 917) The Iran-US Claims Tribunal, sometimes viewed as interstate arbitration and sometimes viewed as international commercial arbitration,82 followed the general tendency of suggesting, while not in fact needing to wield, an inherent power to reconsider its awards in certain extreme circumstances. The Tribunal was faced with repeated requests for reconsideration, fashioned more or less ingeniously under Articles 35–37, but steadfastly defended the finality of awards issued under Article 32(2).83 The Tribunal seemed to endorse the existence of inherent authority to reopen, but never faced a fact situation sufficiently severe to warrant exercising it.

The only extreme circumstances mentioned specifically by the Tribunal were fraud, forgery or false testimony.84 In the 1983 Morris decision, Chamber One stated:

Whether a Chamber or the Full Tribunal, despite the absence of any express provision, has inherent power to review and revise an Award under exceptional circumstances–e.g. when an Award was based on forged documents or perjury–is a question which the Tribunal does not need to reach in this decision.85

In the oft–quoted Dames & Moore decision denying Iran's request for reconsideration, based in part on Articles 35 and 37, on the grounds that Dames & Moore had obtained its award through fraud and forgery, Chamber Three of the Tribunal stated:

The implied or inherent power of an international claims tribunal in this area is an issue which has been subjected to learned analysis, and limited judicial scrutiny, with wholly inconsistent results. The instant request for reopening and reconsideration, however, falls well short of justifying any such effort to ascertain the precise balance struck between finality of Tribunal dispositions, on the one hand, and the integrity of its processes on the other.86

Although fraud was thus referred to as a circumstance perhaps addressed by an inherent power to reconsider, other circumstances, given the Tribunal's (p. 918) silence, apparently did not rise to that level of concern. In Eastman Kodak, “the Respondent describe[d] the legal basis of its objection as ‘the failure to observe the Tribunal's findings in the [earlier] Partial Award, … and the conflict and inconsistency between the Tribunal's findings in the Partial and Final Awards.’ ”87 In other words, it was alleged that the Tribunal's Final Award was inconsistent with, and therefore breached the finality of, the Partial Award. The Tribunal disposed of the request simply noting that this objection did not fall within the scope of Article 35, 36 or 37. The Tribunal did not consider whether an inherent power exists in such a case:

… Insofar as the Respondent's request constitutes an attempt to reargue certain aspects of the Case on which the Respondent disagrees with the Tribunal's conclusions in the Final Award, there is no basis in the Tribunal Rules or elsewhere for review of an award on such grounds.88

Interestingly, the Tribunal did not have to reopen the one award known to have been based on fraud, the now infamous Gordon Williams case.89 In that case, the Tribunal awarded “Mr. Williams” an award of approximately US $300,000. In the course of attempting to pay “Mr. Williams” his award, the New York Federal Reserve Bank received payment instructions from six different “Mr. Williams” and representatives. A New York court ultimately determined that an Iranian national had impersonated a dead US national to pursue the claim. Because the Tribunal unequivocally lacked jurisdiction over claims by Iranian nationals against Iran, the court ordered the New York Fed to return the funds to the Tribunal Security Account. Therefore justice was done without the need for the Tribunal to reopen and nullify its award. The Gordon Williams case demonstrates that there are dramatically real instances of fraud in international commercial arbitration, but that they also are not likely to go unnoticed or unremedied.90

(p. 919) Extracts from the Practice of the Iran-US Claims Tribunal

(1)  Limited power of review

It is obvious, and both Parties are in full agreement, that neither Article VI, paragraph 4 [of the Claims Settlement Agreement] nor the Tribunal Rules provide for any kind of review by the Full Tribunal of Orders or Awards made by the Chambers. To the Contrary, Article IV, paragraph 1, which applies equally to actions by the Full Tribunal and the Chambers, states that “[a]ll decisions and Awards of the Tribunal shall be final and binding”. The only exceptions to this rule of finality are those contained in Articles 35 and 36 of the Tribunal Rules, dealing with interpretation and correction, which clearly do not apply here.

Islamic Republic of Iran and United States of America, Case No. A/20, Decision No. DEC 45–A20–FT (26 Jun 1986), reprinted in 11 Iran-US CTR 271, 274 (1986–II).

The request does not rely on, or fall within, any of the relevant provisions of the Tribunal Rules, and it is questionable whether, even in exceptional circumstances, the Tribunal would have authority to act outside those Rules to revise or correct an award. It is even more questionable whether the Tribunal would have authority to do so where, as here, the Party seeking revision does not complain of any irregularities in the procedure, but merely asserts the existence of legal error in the decision itself.

International Schools Services, Inc. and Islamic Republic of Iran, Award No. 290–123–1 (29 Jan 1987), reprinted in 14 Iran-US CTR 65, 70–71 (1987–I).

[T]he Tribunal is unable to grant the relief sought in the Requests. The Requests allege several procedural and legal errors which the Respondents assert were committed by the Tribunal in the Award, and urge the Tribunal to reconsider its decisions. The Tribunal is without power to entertain the Requests, however, which amount in effect to a request for appeal or review of the Award by the Tribunal.

Sedco, Inc. and National Iranian Oil Company, Decision No. DEC 64–129–3 (18 Sep 1987), reprinted in 16 Iran-US CTR 282, 283–84 (1987–III).

The Rules do not provide for review or appeals. No party should be (p. 920) permitted to relitigate Tribunal awards in the guise of a challenge, no matter how unhappy it may be about the results of the award.

Letter, the US Agent to the Appointing Authority (8 Aug 1989), reprinted in 21 Iran-US CTR 349 (1989–I).

MOA states that its request is based on Articles 36 and 37 of the Tribunal Rules. MOA does not, however, make a request for correction of the award, as provided for in Article 36, nor does it make a request for an additional award, as provided for in Article 37 of the Tribunal Rules. Instead, MOA seeks to reargue certain aspects of the case and to submit additional evidence, in the form of an alleged Settlement Agreement, dated 18 December 1981. The Tribunal finds that MOA has had ample opportunity to present all arguments and submit all evidence it considered relevant. The Tribunal Rules do not provide for additional arguments and evidence after a case has been concluded by Award.

Development and Resources Corporation and Islamic Republic of Iran, Decision No. DEC 98–60–3 (30 May 1991), reprinted in 26 Iran-US CTR 256, 261 (1991–I).

With regard to the request for a correction to the award concerning the amount of $176,304.02 awarded for work performed for the PMS Development at Bandar Abbas, Tribunal precedent is clear. Insofar as the request constitutes an attempt to reargue certain aspects of the Case, to disagree with the conclusions of the Tribunal in its Award, or to request the Tribunal either to review its Award or further to explain its reasons for the Award, there is no basis in the Tribunal Rules for a request of this kind on such grounds.

Unidyne Corporation and Islamic Republic of Iran, Decision No. DEC 122–368–3 (9 Mar 1994), reprinted in 30 Iran-US CTR 19, 20 (1994).

There are both national and international jurisdictions which, while recognizing the final and binding nature of judgments, do not exclude revision thereof.

Where revisions are permitted, they are normally provided for in an express rule of procedure. Decisions by international tribunals which, in the absence of such express provisions, admitted the existence of the inherent power of an international tribunal to revise, under extraordinary circumstances, its own awards, are rather rare and exceptional. There is not much room for reading implied powers into a contemporary (p. 921) bilateral arrangement; for its authors are aware of past experience. It is to be expected that today, two States that intended to allow the revision of awards rendered by a tribunal established pursuant to a treaty between them would do so by unequivocal expression of their common will. Clearly Iran and the United States did not so provide in the Algiers Declarations.

The Tribunal has recognized that it has inherent power to issue certain interim orders… . The revision of a final award, however, belongs to a different category

[T]he final and binding force of an award does not necessarily exclude the possibility of a revision thereof. But the existence of express rules providing that the award is “final and binding,” coupled with the silence of the contracting Parties concerning the possibility of revision, makes it difficult to conclude that any inherent power to revise a final award exists.

Harold Birnbaum and Islamic Republic of Iran, Decision No. DEC 124–967–2 (14 Dec 1995), reprinted in 31 Iran-US CTR 286, 289–90 (1995) (footnotes omitted).

  1. 32.  … Clearly, there is nothing in the Claimant's applications which would fall within the ambit of Articles 35–37 of the Tribunal Rules. The Claimant herself does not suggest this. She is instead urging the Chamber to reconsider its Final Award and to arrange a new legal procedure including the possibility of presenting additional documents and statements by witnesses and eventually a new hearing, too. In other words, the Claimant is making an appeal for a total review of the Award.

  2. 33.  The legal difference between an appeal for a total review of a Final Award and a revision based on Articles 35–37 of the Tribunal Rules is remarkable. While the latter type of request is admissible by definition if it is so based, these Rules do not contain any provision for the admissibility of an appeal for a total or even partial review of a final award… .

Frederica Lincoln Riahi and The Islamic Republic of Iran, Decision No. DEC 133–485–1 (17 Nov 2004), at 13–14, reprinted in (2004) 19(12) MIAR C–1, C–3.

(2)  Revision to address fraud or corruption

The request made by Mr. Dallal is not based on any of the circumstances (p. 922) covered by Articles 35, 36 or 37. Nor is there any provision for the rescission of, or appeal from, an Award of the Tribunal, or for the re–hearing of a case in which an Award has been rendered.

Whether, in the absence of any express provision, the Tribunal has inherent power to review and revise an Award under exceptional circumstances–e.g. when it subsequently transpires that an Award was based on forged documents or perjury–is a question which the Tribunal does not need to reach in this decision.

Mark Dallal and Islamic Republic of Iran, Decision No. DEC 30–149–1 (10 Jan 1984), reprinted in 5 Iran-US CTR 74, 75 (1984–I).

In the absence of an express grant of authority to the Tribunal to reopen and consider cases on the merits after issuance of an award, the question has been posed as to whether an “inherent power” to do so may exist “under exceptional circumstances,” at least where an award “was based on forged documents or perjury.” … The implied or inherent power of an international claims tribunal in this area is an area which has been subjected to learned analysis and limited judicial scrutiny with wholly inconsistent results. The instant request for reopening and reconsideration, however, falls well short of justifying any such effort to ascertain the precise balance struck between finality of Tribunal dispositions, on the one hand, and the integrity of its processes on the other.

… The Tribunal states no opinion as to the existence of the hypothesized power, but rather expressly reserves such questions for future decision should the same be required.

Dames and Moore and Islamic Republic of Iran, Decision No. DEC 36–54–3 (17 Apr 1985), reprinted in 8 Iran-US CTR 107, 117 (1985–I) (footnotes omitted).

On the basis of the foregoing review, it might possibly be concluded that a tribunal, like the present one, which is to adjudicate a large group of cases and for a protracted period of time would by implication, until the adjournment and dissolution of the tribunal, have the authority to revise decisions induced by fraud. However, in view of what follows, this case does not need to be fully pursued and decided for the purposes of the present Case. On the other hand, one requirement, namely, that an application for revision of an award “may be made only when it is based upon the discovery of some fact of such a nature as to be a decisive factor” follows closely the language of all reviewed legal provisions, judicial decisions and views of learned writers. Therefore, the Tribunal (p. 923) holds that for the purpose of a revision the new fact has to be decisive, in the sense that when placed alongside the other facts of the case, earlier assessed, it seriously upsets the balance, and consequently the conclusions drawn by the tribunal.

RAM International Industries, Inc. and Air Force of The Islamic Republic of Iran, Decision No. DEC 118–148–1 (28 Dec 1993), reprinted in 29 Iran-US CTR 383, 390 (1993).

In its present request, Iran does not allege fraud or perjury or submit decisive new evidence. Iran's submissions are far removed from such instances which might possibly give rise to the revision of an award. Iran contests the reasoning by which the Tribunal arrived at its conclusions. The Tribunal is not persuaded by Iran's assertions. Moreover, the request fails to cite any evidence which was not on the record at the time the Tribunal deliberated this Case. Absent any exceptional ground upon which the request is made, the Tribunal need not decide whether it has an inherent or implied power to revise its Award in the present Case.

United States of America and Islamic Republic of Iran, Case No. B36, Decision No. DEC 126–B36–2 (17 Mar 1997), reprinted in 33 Iran-US CTR 56, 59 (1997).

[N]o tribunal can declare itself immune from procedural error or the possibility of fraud, forgery, or perjury that it may not detect. In such hypothetical cases, however, revision of the award could be done only by the Tribunal, if it concluded that it had authority to do so, not by any other court.

Islamic Republic of Iran and The United States of America, Case No. A/27 Award No. 586–A27–FT (5 Jun 1998), reprinted in 31 Iran-US CTR 39, 58 n 11 (1998).

  1. 38.  … So far, neither the Full Tribunal nor any of the Chambers of the Tribunal have been prepared or even willing to formulate any definition of what is meant by the term “inherent power.” This is due to the generally accepted interpretation that is based on the Algiers Declarations (Article IV, paragraphs 1 and 3, in particular, which gives a final and binding nature to the Tribunal's awards and decisions) and on the clear terms adopted by the Tribunal Rules in Article 32(2)… .

  2. (p. 924)
  3. 43.  … [O]n the basis of the Tribunal's jurisprudence, and in the circumstances of this Case, the Tribunal concludes that there is no need to define the inherent power of the Tribunal, if any, or to delineate under what particular circumstances such a power might be invoked. So far, this issue has been discussed especially in relation to possible cases of fraud and perjury and not as a general problem related to reconsideration. Even in that context, the Tribunal has not reached a single decision confirming the existence and the need to apply its “inherent power,” whatever that may be. In the present Case, there has been no mention of any aspect of fraud or perjury, and the Tribunal need not investigate any further the possibility of applying the theory of inherent power insofar as the request for reconsideration of the Award is concerned.

Frederica Lincoln Riahi and The Islamic Republic of Iran, Decision No. DEC 133–485–1 (17 Nov 2004), at 17, 20, reprinted in (2004) 19(12) MIAR C–1, C–6—C–7 (footnote omitted).

  1. 40.  It is clear that the question as to whether or not the Tribunal has an inherent authority to reconsider an Award under certain circumstances has not been decided and therefore has not been foreclosed. While the majority states that the Tribunal has “turned down” the “notion of [such] inherent power,” the cases it cites for this proposition merely held that it was unnecessary on the facts thereof to decide whether or not such authority existed, not that it does not exist. On the contrary, the Tribunal has in many cases in fact expressly reserved the question of whether such inherent authority exists, including those cases cited by the majority, as the majority itself acknowledges… .

Frederica Lincoln Riahi and The Islamic Republic of Iran, Decision No. DEC 133–485–1 (17 Nov 2004), Dissenting Opinion of Judge Brower (17 Nov 2004), at 21–22, reprinted in (2004) 19(12) MIAR D–1, D–7—D–8 (footnote omitted).

Extracts from the Practice of NAFTA Tribunals

  1. 33.  Turning to the issue under Article 15(1) of the UNCITRAL Rules, there is nothing there to suggest that an arbitration tribunal has a broad jurisdiction to reconsider a final and binding award that it has already made. (The possible exception for fraud by a party is here irrelevant). To the contrary, both the ordinary meaning and the context of Article 15(1) lead to the opposite conclusion. (p. 925) Article 15(1) is located in Section III of the Rules, “Arbitral Proceedings”; and it is a general provision that regulates the conduct of the arbitral proceedings. By contrast, Article 32 is to be found in Section IV, “The Award”; and it is concerned with the form and effect of an award. Article 15(1) cannot be read as creating such a huge derogation from Article 32; it has a significantly different subject–matter. Moreover, Article 15(1) requires that a party be given a full opportunity of presenting its case “at any stage of the proceedings”. This accepts that arbitral proceedings may comprise differing stages, as also appears from Article 15(2), and a given stage in the proceedings may of course be brought to an end by a final and binding award. It would both undermine Article 32 and lead to an inequality between the parties if at any time the losing party could seek to re–litigate matters contained in an award simply by invoking Article 15(1) of the UNCITRAL Rules.

Methanex Corp. and The United States of America, Award (NAFTA Chapter Eleven, 3 Aug 2005), at 19 (Part II, Chapter E), available at http://www.state.gov/s/l/c3439.htm. (some footnotes omitted.)

Extracts from the Practice of Other Tribunals

  1. [32]  As provided in Art. 32(2) of the UNCITRAL Rules, the award on jurisdiction and liability which this Tribunal issued on 27 October 1989 was and is “final and binding on the parties.” The UNCITRAL Rules make no provision for reconsidering an award. Arts. 35, 36 and 37 provide that within thirty days of an award a party may request “interpretation” of an award, may request correction of clerical or typographical errors, or may request an additional award covering issues omitted from the award. The present request for reconsideration was not made pursuant to any of these articles, and (apart from the fact that the request was first made more than thirty days after the original award) none of these articles would seem to support the kind of reconsideration that has been requested.

  2. [33]  Nevertheless, a court or Tribunal, including this international arbitral Tribunal, has an inherent power to take cognizance of credible evidence, timely placed before it, that its previous determinations were the product of false testimony, forged documents or other egregious “fraud on the Tribunal.” See United States on behalf of Lehigh Valley Ry. v. Germany, (Sabotage Claims), Mixed Claims Commission, United States and Germany, (p. 926) Opinions and Decisions from 1 October 1926 to 31 December 1932 (1933) at 967; id., Report of the American Commissioner (30 December 1933) at 7–8; id., Opinions and Decisions in the Sabotage Claims (15 June 1939 and 30 October 1939). Certainly if such corruption or fraud in the evidence would justify an international or a national court in voiding or refusing to enforce the award, this Tribunal also, so long as it still has jurisdiction over the dispute, can take necessary corrective action. See the Statute of the International Court of Justice, Art. 61 (permitting revision of an award upon the subsequent discovery of a new decisive fact); ICSID Convention Art. 51 (same); U.S. Arbitration Act, 9 U.S.C. Sect. 10 (permitting judicial annulment of an arbitral award “procured by corruption, fraud or undue means”).

  3. [34]  The present Tribunal would not hesitate to reconsider and modify its earlier award were it shown by credible evidence that it had been the victim of fraud and that its determinations in the previous award were the product of false testimony. However, no such evidence has been adduced. As in many complex cases, this Tribunal has been required to weigh and resolve occasional inconsistencies in the evidence of both sides in this arbitration, and to come to its best determination of the relevant facts. Nevertheless, the Tribunal is satisfied that the material facts on which it based its previous award on jurisdiction and liability, as well as the present award on damages and costs, are sufficiently explained and proved by credible evidence

Antoine Biloune et al. and Ghana Investments Centre et al., Award on Damages and Costs (Ad Hoc UNCITRAL Proceedings 30 Jun 1990), reprinted in XIX YCA 11, 22–23 (1994).

Footnotes:

One commentator contends that this obligation is part of the arbitrators' ethical and post–contractual duties towards the parties. See K Berger, International Economic Arbitration (1993) 637.

In addressing “post–award proceedings” this Chapter does not discuss proceedings relating to the recognition or enforcement of an award initiated under national arbitration laws and international conventions.

The Iran-US Claims Tribunal adopted Article 35 of the UNCITRAL Rules unchanged with the following note: “As used in Article 35 of the UNCITRAL Rules, the term ‘party’ means the arbitrating party.”

Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 180 (Commentary on Draft Article 30(2)). Committee representatives debated whether the term “interpretation” accurately reflected the meaning and purpose of what ultimately became Article 35. Many expressed a preference for the term “clarification” instead. Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 205–07 (1975). Representatives also offered their views on the meaning and purpose of interpretation. Mr. Mantilla–Molina of Mexico stated that interpretation was the clarification of “the purport of the award and the resultant obligations and rights of the parties.” Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 205 (1975). Mr. Rèczei of Hungary observed that interpretation was useful in resolving confusion and ambiguity in the wording of the award arising in cases where the award was not rendered in the native language of the parties. Ibid at 206.

See Wintershall AG, Final Award and Interpretation, reprinted below section E. This was generally not the case in arbitration before the Iran-United States Claims Tribunal where the Tribunal was addressing “commercial relations that had been broken off and frozen by decades long hostility.” S Baker & M Davis, The UNCITRAL Arbitration Rules in Practice: The Experience of the Iran-United States Claims Tribunal (1992) 194.

Parviz Karim–Panahi, reprinted below section C. See also Methanex, reprinted below section D. See E Gaillard & J Savage (eds), Fouchard, Gaillard, Goldman on International Commercial Arbitration (1999) 776. Nor does the interpretation process permit a party to ask the arbitral tribunal how to meet the obligations set forth in the award. See United States and Iran (Case No. B36), Decision No. DEC 128–B36–2 (23 May 1997), reprinted in 33 Iran-US CTR 346, 348 (1997) (Tribunal has no jurisdiction to order a refund by the United States to the Security Account of funds alleged by Iran to have been improperly withdrawn). Likewise, in Haya de la Torre, the ICJ refused a request from the Colombian Government to indicate whether it was bound “in execution of the … Judgment of November 20th 1950” to hand over Haya del la Torre to the Peruvian Government. Haya de la Torre Case (Colom v. Peru) 1951 ICJ 79 (June 13). See also G Fitzmaurice, The Law and Procedure of the International Court of Justice (1986) 555–56.

See also Request for Interpretation of the Judgment of 20 November 1950 in the Asylum Case, (Colom v. Peru) 1950 ICJ 403 (November 27) (“The ‘gaps’ which the Colombian Government claims to have discovered in the Court's Judgment in reality are new questions, which cannot be decided by means of interpretation.”).

The inherent authority of an arbitral tribunal to re–open a case in exceptional circumstances, another argument raised by Iran, is discussed in detail below in Section 5.

10  See, e.g. Ford Aerospace; Picker International Corporation; Pepsico, Inc.; Paul Donin de Rosiere; American Bell International; Endo Laboratories, Inc.; Uiterwyk Corporation; Phibro Corporation, Norman Gabay reprinted below, section C.

11  K Carlston, The Process of International Arbitration (1946) 241; Hyde, International Law Chiefly As Interpreted by the United States (2d edn, 1945) 1628–29; I Schwarzenberger, International Law (1945) 428–29.

12  Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 207 (1975) (Comment by Mr. Chafik, Egypt). Articles 1060 and 1061 of The Netherlands Arbitration Act 1986, for example, expressly permit rectification, correction, and additional awards, but not interpretation.

13  Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 206 (1975) (Comments by Mr. Bennet, Australia, and Mr. Takakuwa, Japan).

14  Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 180 (Commentary on Draft Article 30(2)). See also K Berger above, n 1, at 641; JL Simpson & H Fox, International Arbitration: Law and Practice (1959) 245. By way of contrast, Article 33(1)(b) of the Model Law permits the arbitral tribunal to give an interpretation only if the parties have agreed to such action before or at the time of the request. For commentary, see H Holtzmann & J Neuhaus, A Guide to the UNCITRAL Model Law on Commercial Arbitration: Legislative History and Commentary (1989) 890.

15  This phrase was meant to underscore that an interpretation was “necessarily and authoritatively linked” to the award to which it corresponds. Report of the UNCITRAL on the Work of its Ninth Session, UN GAOR, 31st Session, Supp No. 17, UN Doc A/31/17, para 191 (1976), reprinted in (1976) VII UNCITRAL Ybk 66, 79.

16  See Chapter 22 on the form and effect of the award.

17  See P Sanders, “Commentary on UNCITRAL Arbitration Rules”, (1977) II YCA 172, 213; S Baker & M Davis above, n 6, at 193.

18  For a summary of the case, see J Carver & K Hossain, “An Arbitration Case Study: The Dispute That Never Was,” (1990) 5 ICSID Rev–FILJ 311.

19  Article 1061 of The Netherlands Arbitration Act of 1986.

20  See Wintershall AG, Final Award, para 5, reprinted below section E.

21  The tribunal placed significant weight on the fact that the Minister of Justice of The Netherlands “referred to the new [Dutch] Act duly taking into account the Model Law … which expressly provides in Article 33 for an interpretation of an award, if so agreed by the parties.” See Wintershall AG, Final Award, para 4, reprinted below section E. Other commentators, however, have maintained that a provision on interpretation was intentionally omitted from the Dutch Act due to the drafters' concerns that such a procedure might be abused by the parties. See J van den Berg, “National Reports (The Netherlands), (1987) 12 YCA 3, 27; H Duintjer Tebbens, (1987) 34 Netherlands International Law Review 146, 155 n 60. For this reason, Article 1058, Section 2 of the new Dutch Act dealing with the termination of the arbitrators' mandate upon deposit of the last final award does not contain a provision allowing the parties to extend the mandate in cases other than those mentioned in Article 1060 et seq. of the new Act. Note that Berger takes the extreme position that providing an interpretation, where forbidden by the governing arbitration law, is a violation of Article 1(2) of the UNCITRAL Rules. See K Berger above, n 1, at 643, 644 note 433.

22  See also Methanex, para 3, reprinted below section D. By way of contrast to the UNCITRAL Rules, the drafters of the ICSID Convention rejected a proposal providing that an interpretation would have the legal effect of being part of the award. See C Schreuer, The ICSID Convention: A Commentary (2001) 862.

23  However, upon closer scrutiny, the real problem with the award was the tribunal's failure to undertake any assessment of the cited provisions of the Exploration Agreement in the Partial Award. See below, section 4.

24  For a discussion of the time limits, see Chapter 14, section 3.

25  See Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 2, para 3 (1976) (Comment by Mr. Pirrung, Federal Republic of Germany).

26  Ibid, para 4 (Comment by Mr. Mantilla–Molina, Mexico).

27  Report of the UNCITRAL on the Work of its Ninth Session, UN GAOR, 31st Session, Supp No. 17, UN Doc A/31/17, para 190 (1976), reprinted in (1976) VII UNCITRAL Ybk 66, 79.

28  If a request was dismissed for lack of timeliness, the Tribunal did not feel it necessary or appropriate to address the substantive question of whether the rendering of an interpretation would have been required. See Component Builders Inc.; International Technical Products Corporation; McCollogh & Company; FMC Corporation, reprinted below, section C.

29  P Sanders above, n 17, at 213.

30  See, e.g. Phibro Corporation (interpretation provided almost 10 weeks after request); Ford Aerospace & Communications Corporation (interpretation provided almost nine weeks after request), reprinted below, section C.

31  The Iran-US Claims Tribunal adopted Article 36 of the UNCITRAL Rules unchanged with the following note: “As used in Article 36 of the UNCITRAL Rules, the term ‘party’ means the arbitrating party.”

32  Harold Birnbaum, reprinted below, section C(2).

33  See, e.g. Uiterwyk Corporation and Vivian May Tavakoli, reprinted below, section C(1); Avco Corporation, para 5, reprinted below, section C(2).

34  See, e.g. American International Group, Inc.; Uiterwyk Corporation; Control Data Corporation, reprinted below, section C(1).

35  In one case, however, the Tribunal “corrected” an award by deleting the description of a letter as “undated.” See, e.g. Component Builders Inc., reprinted below, section C(1).

36  Picker International Corporation; Petrolane, Inc., reprinted below, section C(2).

37  See above, Section 2, at 880.

38  Although mandatory, the drafters seemed less concerned about compliance with Articles 32(3) and 32(6) because Article 36 was meant to address only small changes in the text of the award. See Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 3, para 18 (1976) (Comment by Mr. Sanders, Special Consultant).

39  See, e.g. Paul Donin De Rosiere, reprinted below, section C(2) (correcting an interim award).

40  Bank Markazi Iran, reprinted below, section C(2).

41  See, e.g. American Bell International, Inc.; Harris International Telecommunications; Case No. B36, reprinted below section C(2). See also JL Simpson & H Fox above, n 14, at 241.

42  See, e.g. Component Builders Inc., reprinted below, section C(2).

43  Ibid.

44  See, e.g. Paul Donin de Rosiere, reprinted below, section C(2).

45  The only significant dispute to arise during the drafting of Article 36 was in regard to the parties' 30–day time limit for making a request for correction. Some representatives spoke in favor of no time limit. Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 207 (1975) (Comments by Mr. Ganske, Federal Republic of Germany, Mr. Melis, Australia, and Mr. Eyzaguirre, Chile). See also Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 3, para 15 (1976) (Comment by Mr. Guevara, Philippines). One delegate suggested that the proposed time limit for requesting corrections to an award run, not from the date of the award, but from the time the parties were required to discharge their obligations. See Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 208 (1975) (Comment by Mr. Réczei, Hungary). Another representative argued that when it came to dealing with requests for correction the window of opportunity “could not be left open indefinitely.” Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 3, para 16 (1976) (Comment by Mr. Mantilla–Molina, Mexico).

46  Note, however, that tardiness has been a leading basis for rejection of a correction request before the Iran-US Claims Tribunal. See, e.g. Component Builders Inc., reprinted below section C(2). See also International Technical Products, reprinted above, section 2(C).

47  A Vollmer & A Bedford, “Post–Award Arbitral Proceedings” (1998) 15(1) JIA 37, 49, warn that “a party could delay finality for substantial periods by filing request after request.” We do not agree. The thirty–day time limit does not reset each time corrections to the award are made. It is theoretically possible, however, that an additional thirty–day period would exist for a valid request to correct a previously corrected award.

48  Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 180 (Commentary on Draft Article 32(2)).

49  See, e.g. Harold Birnbaum, reprinted below, section C(1).

50  For a discussion of the legal effect of a correction, see below, section 3.

51  The Iran-US Claims Tribunal has adopted Article 37 of the UNCITRAL Rules unchanged with the following note: “As used in Article 37 of the UNCITRAL Rules, the term ‘party’ means the arbitrating party.”

52  Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 180 (Commentary on Draft Article 32).

53  Ibid.

54  Ibid.

55  Ibid.

56  See K Berger above, n 1, at 637. Article 32(1) of the Model Law provides: “The arbitral proceedings are terminated by the final award… .”

57  An additional award, like all awards rendered under the Rules, is subject to the rule of majority voting, pursuant to Article 31.

58  Professor Sanders observed that Article 37 “was intended to cover obvious cases of omission on the part of the arbitrators, in other words cases in which, although all the elements necessary for an award had been submitted, the arbitrators had not rendered a complete award.” Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 4, para 22 (1976). See also P Sanders (1977) above, n 29, at 214.

59  See, e.g. Assistance in Developing Educational System, Inc., reprinted below section C(1).

60  Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 180 (Commentary on Draft Article 32(1)).

61  Summary Record of the 151st Meeting of the UNCITRAL, 8th Session, UN Doc A/CN.9/SR.167, at 208 (1975) (Comment by Mr. Krispis, Greece). See also Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 4, para 25 (1976).

62  The commentary on the Revised Draft explains that the arbitrators have “full discretion, upon receipt of the request of a party for an additional award, to decide whether or not to make such an award.” Report of the Secretary–General on the Revised Draft Set of Arbitration Rules, UNCITRAL, 9th Session, Addendum 1 (Commentary), UN Doc A/CN.9/112/Add.1 (1975), reprinted in (1976) VII UNCITRAL Ybk 166, 181 (Commentary on Draft Article 32(2)).

63  Woodward–Clyde Consultants; Flexi–Van Leasin; International Schools Services, Inc.; Exxon Research and Engineering Company; Reza and Shahnaz Mohajer–Shojaee; Esahak Saboonchian, reprinted below section C(2).

64  Harris International Communications, Inc., reprinted below section C(2).

65  Iran and the United States Case No. A/27, reprinted below, section C(2).

67  Thus, additional awards may be rendered only on the basis of “evidence that the arbitrators had before them at the time that they made they made their original, incomplete award.” Ibid at 181.

68  Summary Record of the 12th Meeting of the Committee of the Whole (II), UNCITRAL, 9th Session, UN Doc A/CN.9/9/C.2/SR.12, at 3–4, para 21 (1976) (Comment by Mr. Lebedev, USSR).

69  Ibid at 4, para 25 (Comments by Mr. Pirrung, Federal Republic of Germany).

70  See P Sanders (1977) above, n 29, at 214.

71  See H Holtzmann & J Neuhaus, above n 14, at 891 (commenting on Article 33(3) of the Model Law).

72  Ibid.

73  The decision to modify need not be made formally, pursuant to Article 1, but may be made as the need arises in accordance with Article 30. See Chapter 20.

74  For a discussion regarding the timing of submissions, see Chapter 10.

75  See, e.g. Hood Corporation, reprinted below, section C(2).

76  Note that Article 33(4) of the Model Law permits the arbitral tribunal to extend the period of time for making a correction, interpretation, or an additional award, if necessary. For discussion, see H Holtzmann & J Neuhaus above, n 14, at 891–92.

77  Such authority cannot be derived from Article 15(1) of the UNCITRAL Rules. See Methanex, reprinted below, section C.

79  Under Article V(2)(b) of the New York Convention, recognition and enforcement of an arbitral award may be refused if the competent authority in the country where recognition and enforcement is sought finds that recognition and enforcement would be contrary to the public policy of that country. The US Federal Arbitration Act allows for the setting aside of an award procured by corruption, fraud, or undue means. 9 USC § 10 (1995).

80  Antoine Biloune, para 34, reprinted below, section D.

81  As to “inherent powers,” see generally D Caron, “Interim Measures of Protection: Theory and Practice in Light of the Iran-United States Claims Tribunal,” (1986) 46 Zeitschrift für ausländisches öffenliches Recht und Völkerrecht 465, 473–480.

82  See generally D Caron, “The Nature of the Iran-United States Claims Tribunal and the Evolving Structure of International Dispute Resolution,” (1990) 84 AJIL 104–156.

83  For discussion of the issue by the Tribunal, see below section B(1). See also G Aldrich, The Jurisprudence of the Iran-United States Claims Tribunal (1996) 452.

84  See below, section B(2).

85  Henry Morris and The Government of the Islamic Republic of Iran et al., Dec No. DEC 26–200–1 (16 Sep 1983), reprinted in 3 Iran-US CTR 364, 364–65 (1983–II).

86  Dames and Moore and The Islamic Republic of Iran, Dec No. DEC 36–54–3 (23 Apr 1985), reprinted in 8 Iran-US CTR 107, 117 (1985–I) (footnotes omitted).

87  Eastman Kodak Co. and Islamic Republic of Iran, Dec No. DEC 102–227–3 (30 Dec 1991), reprinted in 27 Iran-US CTR 269, 269 (1991–II).

88  Ibid at 271.

89  Gordon Williams and Islamic Republic of Iran et al., Award No. 342–187–3 (18 Dec 1987), reprinted in 17 Iran-US CTR 269 (1987–IV).

90  See Remarks by Jacomijn van Hof on the topic of a tribunal's inherent authority to reconsider awards in the Proceedings of the 1993 Joint Dutch–American Meeting of International Law Societies at 8–13. Ms. van Hof suggests that the Tribunal can and should address the issue of fraud in the Gordon Williams case in the course of conducting the final reconciliation of the Security Account.