Footnotes:
1 Born, p 2074. On consolidation and joinder/intervention in international arbitration see in particular Meier.
4 See Berger, Arbitration, pp 311–312. The tribunal’s consent is requested because the intervention or joinder of a third party may lead to a substantial increase in the workload of the arbitrators and a modification of the proceedings (hearing dates, projected time for the whole arbitration, etc); however, if the parties have all agreed to the intervention, the tribunal will usually not refuse to give its consent (ibid, footnote 718).
13 Derains and Schwartz, p 58, who, however, also observed that there was nothing in the ICC Rules that mandated such a strict position.
16 Whether voluntary or under compulsion.
19 Article 7(2)(c) of the ICC Rules (2012) in conjunction with Art 4(3)(e) of the ICC Rules (2012).
21 Emphasis added. The term ‘Court’ clearly means the International Court of Arbitration of the ICC.
23 Claimant or respondent.
24 This does not, however, cover the possibility of joining a third party in relation to a counterclaim (see Lew, Mistelis, and Kröll, p 390 at footnote 33).
29 And this provision has been used very sparingly and very rarely granted (Bamforth and Maidment, p 12). As at the end of 2008, approximately 12 applications had been made under Art 22(1)(h), of which five were granted and one case was settled before a decision had been made (Nesbitt in Mistelis (ed), Concise, para 9 at Art 22 of the LCIA Rules).
30 The beginning of Art 22(1) of the LCIA Rules states: ‘Unless the parties at any time agree otherwise in writing’.
40 See Art 4(1) of the Swiss Rules.
42 Following the UNCITRAL Rules.
43 Awards of 27 October 1989 and 30 June 1990, XIX YBCA (1994), pp 11 et seq.
44 See Awards of 27 October 1989 and 30 June 1990, XIX YBCA (1994), paras 12 et seq.
45 See Art 22 of the UNCITRAL Rules (2010): ‘However, a claim or defence, including a counterclaim or a claim for the purpose of a set-off, may not be amended or supplemented in such a manner that the amended or supplemented claim or defence falls outside the jurisdiction of the arbitral tribunal.’ See also Berger, Arbitration, pp 311–312.
48 Art 6(4)(i) of the ICC Rules (2012).
49 This used to be the case in international multiparty arbitrations conducted under the Zurich Rules. On the Zurich Rules see Karrer.
50 This is not the case in France. See Cour de Cassation, 7 January 1992, Siemens AG/BKMI Industrieanlagen GmbH v Dutco Construction Company, XVIII YBCA 140 (1993). For a discussion of the Dutco case see, eg Bellet; Delvolvé, Dutco.
52 See, eg the LCIA Rules or the Swiss Rules. Here the consent of the initial parties is given, because they submitted their dispute under the said arbitration rules. Thus, afterwards, only the consent of the new joining third party is necessary. See also Melnyk, p 63. On this aspect see, eg the decision by the Privy Council in The Bay Hotel and Resort Ltd v Cavalier Construction Co Ltd [2001] UKPC 34, 17(1) Mealey’s IAR B-1 (2002), B-7 et seq.
53 Art 1696bis of the Belgian Judicial Code.
54 Art 1045 of the Netherlands CCP.
57 For a detailed analysis of the advantages of consolidation generally, see Chiu.
60 For a detailed analysis of the disadvantages of consolidation generally, see Chiu.
63 See, eg Lew, Mistelis, and Kröll, para 16–75. See also Diamond and in particular Collins discussing the case Oxford Shipping Company Limited v Nippon Yusen Kaisha (‘The Eastern Saga’) [1984] 2 Lloyd’s Rep 373 (QB).
66 ibid. See also Art 15(8) of the Vienna Rules which explicitly requires that ‘all parties and the sole arbitrator (arbitral tribunal) agree’.
68 Lew, Mistelis, and Kröll, para 16–51. One example where the parties agreed on consolidation after the dispute has arisen is ICC Case No 6719 (on ICC Case No 6719, see Arnaldez, Derains, and Hascher, Collection of ICC Arbitral Awards 1991–1995, pp 567 et seq).
70 Lew, Mistelis, and Kröll, para 16–51. In fact, most recommended institutional arbitration clauses are based upon the traditional two-party model. Attempts to propose multiparty arbitration clauses were, however, undertaken by scholars. See, eg Bartels; Wetter, Multi-party.
71 See IBA Guidelines for Drafting International Arbitration Clauses, paras 97 et seq.
77 Clause 18(2) of the FCEC Standard Form of Subcontract states: ‘If any dispute arises in connection with the main contract and the contractor is of the opinion that such dispute touches or concerns the subcontract works, then provided that an arbitrator has not already been agreed or appointed in pursuance of the preceding sub-clause, the contractor may by notice in writing to the subcontractor require that any such dispute under this subcontract shall be dealt with jointly with the dispute under the main contract in accordance with the provisions of clause 66 thereof. In connection with such joint dispute the subcontractor shall be bound in like manner as the contractor by any decision of the engineer or any award by an arbitrator.’
84 See Final award in Case No 9797 of 28 July 2000, ASA Bulletin, Vol 18, No 3 (2000), pp 514–540, Summary of the proceedings.
85 Decision of the Swiss Federal Tribunal of 8 December 1999, ASA Bulletin, Vol 18, No 3 (2000), pp 546–557.
89 On the Sofidif case, see CA de Versailles (Chambres réunies), 7 March 1990, OIAETI et Sofidif v COGEMA, SERU, Eurodif, CEA, Note E Loquin, Rev Arb, 1991 No 2, pp 326–344.
93 Art 10(a) of the ICC Rules (2012).
94 Art 10(b) of the ICC Rules (2012).
95 See Art 10 of the ICC Rules (2012). On Art 10 of the ICC Rules (2012), with the heading ‘Consolidation of Arbitrations’ see Voser, pp 796 et seq.
101 Provided that the joining parties have also agreed on the Swiss Rules.
110 The DAC received many submissions—the majority of them coming from the construction industry—which called for a provision that would empower either a tribunal and/or the court to order consolidation or concurrent hearings.
111 Landau, English Arbitration Act, p 117; DAC Report of February 1996, para 180.
114 Hong Kong now has a new Arbitration Ordinance (2010), (Cap 609) which creates a unitary regime for domestic and international arbitrations.
115 The provision does not regulate consolidation of connected arbitral proceedings before the same arbitral tribunal (Sanders, Quo vadis, p 219).
116 As consolidation under Art 1046 of the Netherlands CCP is only possible between arbitral proceedings taking place in the Netherlands, it will be rare that international arbitrations will be subject to consolidation under this provision.
117 Sanders, Quo vadis, p 219. See also Miller, p 90; and Sanders, The New Dutch Arbitration Act, p 201, who indicated that the parties may in practice opt out of the possibility of consolidation by reference to the rules of an arbitration institute.
121 See also para 3(5)(d) of the Introduction to NAI Arbitration Rules.
122 Where arbitrations in the building industry take place (Sanders, Quo vadis, p 219; see also Sanders, The New Dutch Arbitration Act, p 201).
123 See Art 1046(3) of the Netherlands CCP.
124 See Art 1046(4) of the Netherlands CCP.
129 Orders for consolidation or concurrent hearings tend to be prevalently made in relation to construction arbitrations.
131 On the first Shui On case ([1986] HKLR 1177), see Miller and Veeder, Consolidation. On the second Shui On case ([1987] HKLR 1224), see Veeder, Consolidation.
134 See s 22 of the Australian International Arbitration Amendment Act 1989.
135 For Australia, see also Croft.
138 For the case of related proceedings before the same arbitral tribunal, see s 24(4) of the Australian International Arbitration Amendment Act 1989. For the case of related proceedings before two or more arbitral tribunals, see paras (5)–(7) of s 24 of the Australian International Arbitration Amendment Act 1989.
140 See s 2 (Second Schedule) of the New Zealand Arbitration Act 1996 (Consolidation of arbitral proceedings).
144 527 F 2d 966 (2d Cir 1975).
145 Born, p 2079, citing, eg P/R Clipper Gas v PPG Indus, Inc, 804 F.Supp 570, 575 (SDNY 1992); N River Ins Co v Philadelphia Reins Corp, 1991 WL 90735, at *3 (SDNY 1991); Rio Energy Int’l, Inc v Hilton Oil Transport, 776 F Supp 120 (SDNY 1991); Benship Int’l v Phosphate Chem Exp Ass’n, 771 F Supp 87, 88–89 (SDNY 1991). For further examples see Born, p 2079, footnote 56.
146 See in particular Gov’t of United Kingdom of Great Britain and Northern Ireland v Boeing Co, 998 F 2d 68 (2d Cir 1993).
147 See, eg Cal CCP § 1281.3.
148 Born, p 2088, mentioning, eg Mass Gen Laws Ann, C 251, § 2A; Tex Civ Prac & Rem Code Ann §172.173. For further examples see ibid, footnote 100.
151 See s 10(c) of the RUAA.
152 In fact, even in the absence of express prohibitions on consolidation, the legitimate expectations of contracting parties may limit the ability of courts to consolidate arbitration proceedings (Comment on s 10 of the Uniform Arbitration Act 2000, p 38).
153 Born, p 2089, citing in footnote 103, eg Huber, Hunt & Nichols, Inc v Architectural Stone Co, 625 F 2d 22, 25–6 (5th Cir 1980); Home Ins v New England Reins Corp, 1999 US Dist LEXIS 13421 (SDNY 1999); Ore & Chem Corp v Stinnes Interoil, Inc, 606 F Supp 1510 (SDNY 1985).
155 See paras 10.42 et seq.
160 See also Lew, Mistelis, and Kröll, para 16–87. Both parties are only restricted in so far as they cannot appoint different arbitrators for each arbitration—though there are situations where parties do not wish to appoint the same arbitrator for the two arbitrations.
164 The term ‘Court’ clearly means the International Court of Arbitration of the ICC.
168 See Art 4(1) of the Swiss Rules.
169 See Art 12 of the CEPANI Rules.
170 For the Swiss Rules see para 10.38. For the CEPANI Rules see para 10.37.
172 Schneider, p 110. An interesting solution to this issue was found by an American court in the case Dale Metals Corp and Overseas Development Corp v KIWA Chemical Industry Co Ltd et al (IV YBCA (1979), pp 333 et seq). On this case, see also Schneider.
176 Or de facto consolidation.
180 Abu Dhabi Gas Liquefaction Co Ltd v Eastern Bechtel Corp [1982] 2 Lloyd’s Rep 425.
182 Abu Dhabi Gas Liquefaction Co Ltd v Eastern Bechtel Corp [1982] 2 Lloyd’s Rep 425, p 427.
184 Shui On Construction Company Limited v Moon Yik Company Limited, et al, and Schindler Lifts (Hong Kong) Limited v Shui On Construction Company Limited, Supreme Court of Hong Kong, High Court, Docket 1985 No MP2114, judgment dated 12 September 1986 (Rhind J); or Shui On Construction Company Limited v Moon Yik Company Limited, et al (1989) XIV YBCA 215.
187 A mechanism in which all arbitrators are appointed by the institution is the one of the Zurich Rules (see also Reymond, Connaissances, p 17).
189 See Lew, Mistelis, and Kröll, para 16–80. Reaching the consent of all parties could therefore be difficult; if not provided in the arbitration agreement none of the parties can be forced to appoint an arbitrator who would also be suitable for the other arbitration (ibid).
191 See under the Hong Kong Arbitration Ordinance (1997), Art 6(B)(1)(c).
195 Aerospatiale Holdings Australia Pty Ltd et al v Elspan International Pty Ltd (Hong Kong), XIX YBCA 635 (1994), no 55053/92 (Supreme Court of New South Wales, 14 August 1992).
197 As was observed by the Court: see Aerospatiale Holdings Australia Pty Ltd et al v Elspan International Pty Ltd (Hong Kong), XIX YBCA 635 (1994), no 55053/92 (Supreme Court of New South Wales, 14 August 1992), paras 14–15.
198 Lew, Mistelis, and Kröll, para 16–83. See, eg the decision of the US Supreme Court in Volt Information Sciences, Inc v Board of Trustees of Leland Stanford Junior University, 109 S Ct 1248 (1989), in XV YBCA 131 (1990), where, however, the parties had agreed to arbitrate in accordance with Californian law and such a possibility was expressly provided for in the applicable Californian statute (Cal Civ Proc Code Ann Sect 1281.2(c)).
205 See Art V(1)(a) of the New York Convention.
206 See Art V(1)(b) of the New York Convention.
209 See, eg Swiss Rules. The consent is given in an indirect way by making reference to the arbitration rules.
210 See the discussion between Van den Berg, Consolidated and Replique and Jarvin, Critique.